Question #: 71
Topic #: 8

A project manager and project team are developing a strategic approach to engage the internal and external stakeholders. Which approach should be followed?


A.

Schedule status meetings with all stakeholders to allow their participation in all project discussions and reports.


B.

Analyze both internal and external stakeholders and develop a customized engagement strategy for each stakeholder.


C.

Involve only the internal stakeholders, as the external stakeholders should not have access to confidential information.


D.

Classify all high-risk stakeholders and request that the project sponsor communicate directly with them.