Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 60 Topic 7 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 60 Topic 7 Discussion

PMP Exam Topic 7 Question 60 Discussion:
Question #: 60
Topic #: 7

A project manager finds an unexpected issue halfway through a customer's protect After analysis the project team determines that the issue will affect the timeline unless more resources are allocated to the project.

What should the project manager do?


A.

Meet with the project team to discuss internally whether they think cost is more important to the customer than the timeline


B.

Adjust the timeline since in the past the customer would not pay any additional costs then inform the customer of the change


C.

Inform the customer of the issue and discuss the options so that they are able to make a decision on cost versus timeline


D.

Absorb the additional cost for the additional resources internally so that the project completes within the timeline


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.