PMI Project Management Professional (2025 Version) PMP Question # 60 Topic 7 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 60 Topic 7 Discussion

PMP Exam Topic 7 Question 60 Discussion:
Question #: 60
Topic #: 7

A project manager for a software technology project works in a matrixed organization with virtual teams. Unfortunately, the functional manager informs the project manager that there may not be any resources available to test the software.

What should the project manager do next?


A.

Engage with the functional manager to discuss details to obtain the required support.


B.

Request a teleconference meeting with the sponsor to submit a change request to allow the development team to conduct testing.


C.

Discuss testing requirements at the weekly project meeting to negotiate the best approach to test software.


D.

Send an email to the procurement specialist to negotiate with a company that specializes in software testing.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.