PMI Project Management Professional (2025 Version) PMP Question # 131 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 131 Topic 14 Discussion

PMP Exam Topic 14 Question 131 Discussion:
Question #: 131
Topic #: 14

A product owner presented the backlog to the team, and the team raised concerns over implementing some of the features due to various impediments What should the project manager suggest that the product owner do next?


A.

Ensure that the impediments are captured and prioritized based upon the highest valued features


B.

Estimate the financial impact of the impediments and request additional funding


C.

Begin to remove the impediments, starting with the easiest ones first, to foster team accomplishment


D.

Capture the impediments and inform management that their assistance is needed

in resolving the impediments


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.