PMI Project Management Professional (2025 Version) PMP Question # 131 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 131 Topic 14 Discussion

PMP Exam Topic 14 Question 131 Discussion:
Question #: 131
Topic #: 14

A supplier that the company has used for years has trouble accepting the new terms of an agile contract. They do not understand the terms in the contract and feel they should not have to sign it because they have had a long relationship with the company.

Which action should the project manager take?


A.

Ask the team if they can do the work until there is an available supplier.


B.

Train the supplier in agile approaches to help them understand the contract.


C.

Issue a request for proposal (RFP) to find new suppliers with agile experience.


D.

Change contract terms and conditions to avoid losing the supplier.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.