New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 131 Topic 14 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 131 Topic 14 Discussion

PMP Exam Topic 14 Question 131 Discussion:
Question #: 131
Topic #: 14

A project is in the execution phase. The client was actively involved in the early stages but has been less engaged lately. A number of changes to the requirements have

recently been requested.

What should the project manager do next?


A.

Reject the changes and stay the original course as initially agreed with the client.


B.

Review the changes and make the decision based on the project team's recommendations.


C.

Discuss the changes with the client and jointly make the decision on how to proceed.


D.

Review the risk register to see if mitigations have already been outlined for this scenario.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.