New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 62 Topic 7 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 62 Topic 7 Discussion

PMP Exam Topic 7 Question 62 Discussion:
Question #: 62
Topic #: 7

A project is on schedule. However, during a site visit, a project manager notices that the contractor's productivity is low.

What should the project manager do?


A.

Assess the opportunity to deliver the project ahead of schedule and introduce a reward system.


B.

Discuss the need to increase productivity with the contractor.


C.

Plan the close-out activities since the project is on schedule.


D.

Update the project schedule to align with the contractor's productivity.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.