PMP Exam Topic 7 Question 62 Discussion:
Question #: 62
Topic #: 7

An agile project for a database migration impacts nearly all business units of the corporation. Every effort has been made to complete the migration before the end-of-support date for the database platform. A new impediment now implies the need to continue use of the old platform another year at a higher support price.

What should the product owner do about this situation?


A.

Reprioritize the backlog based on value and cost of delay divided by duration.


B.

Switch to a predictive approach to prevent any further delays to completion.


C.

Reprioritize the backlog based on story size and competence availability.


D.

Remove low-value items from the backlog to compensate for the higher cost.