Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 62 Topic 7 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 62 Topic 7 Discussion

PMP Exam Topic 7 Question 62 Discussion:
Question #: 62
Topic #: 7

A project manager assigned to an engineering construction project is receiving questions from the site engineers. Several questions are related to carrying out activities to meet timelines that compromise the work crew's safety. When reviewing these questions, the project manager realizes that the engineers do not (eel empowered to make decisions.

How should the project manager address this?


A.

Consult the previous project manager to discuss how they managed these questions.


B.

Ensure all engineers are aware that questions should only be submitted in their weekly reports.


C.

Email the company vision to the engineers and tell them they need to meet deadlines


D.

Reinforce to all engineers the company vision of a safety-first approach to project activities.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.