Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 74 Topic 8 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 74 Topic 8 Discussion

PMP Exam Topic 8 Question 74 Discussion:
Question #: 74
Topic #: 8

During a scope validation exercise toward the end of a project, a project manager realizes that some operational project requirements were not captured in the project scope of work. Although completing these Items will have an Impact on the project's completion date. It will Increase the likelihood of customer acceptance.

What should the project manager do to address the issue?


A.

Issue a change request to remove items from the scope of work and keep the project on schedule.


B.

Issue a change request to include the additional scope, and track the completion of the work items.


C.

Document the issue in the lessons learned document, and discuss this with the project sponsor.


D.

Arrange to pass the cost to the operational area since the customer will benefit.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.