New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 74 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 74 Topic 8 Discussion

PMP Exam Topic 8 Question 74 Discussion:
Question #: 74
Topic #: 8

In an agile project, the team decided to have a rotating group of facilitators for the daily scrum. Overall, most of the facilitators have grown and done well in this role; however, a few of them tend to run inefficient daily scrums.

What should the project manager do next?


A.

Retrain all team members on daily scrum facilitation to ensure there is consistency in the approach.


B.

Ask the facilitators who are doing well to continue and recommend that the others stop facilitating.


C.

Praise the team for self-organizing and growing, then work one-on-one with the facilitators, as needed.


D.

Return to using the scrum master as the facilitator for the daily scrums now that the trial period is over.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.