New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 73 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 73 Topic 8 Discussion

PMP Exam Topic 8 Question 73 Discussion:
Question #: 73
Topic #: 8

A project manager is assigned to a multiyear project. During project execution, the customer delegates a new representative who contacts the project manager directly with a concern about their participation in status meetings. The representative wants to contact team members directly.

What should the project manager do next?


A.

Send the new representative the approved project management and communications management plans.


B.

Reach out to the customer directly for assistance in incorporating the new representative into the project management plan.


C.

Meet with the project sponsor to discuss how to incorporate the new representative in the project.


D.

Meet with the new representative to determine their understanding of the project and address their concerns.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.