PMI Project Management Professional (2025 Version) PMP Question # 73 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 73 Topic 8 Discussion

PMP Exam Topic 8 Question 73 Discussion:
Question #: 73
Topic #: 8

A project is on its fourth iteration out of six. During iteration planning, a team member informs the project manager that their computer is not working.

What should the project manager do next?


A.

Suggest that the team member contact the IT department.


B.

Facilitate a priority resolution of the issue with the IT department.


C.

Update the issue log and escalate the problem to the product owner.


D.

Ask the other team members to step in and do the work.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.