Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 73 Topic 8 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 73 Topic 8 Discussion

PMP Exam Topic 8 Question 73 Discussion:
Question #: 73
Topic #: 8

A project manager is managing two integrated projects in a program A key integration point is misaligned, which has resulted in delays. One of the team's integration leads is a subject matter expert (SME) m this integration area. The other team's integration lead is not a SME but is more senior and has worked on the project longer Both team leads are blaming each other

What should the project manager do first to resolve this situation?


A.

Assign the resolution of the issue to the senior integration lead who has worked on the project longer


B.

Meet with both integration leads to understand the root cause and determine a resolution


C.

Escalate the issue to the program architect who developed the integration plan


D.

Assign the resolution of this issue to the integration lead who is a SME


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.