PMI Project Management Professional (2025 Version) PMP Question # 73 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 73 Topic 8 Discussion

PMP Exam Topic 8 Question 73 Discussion:
Question #: 73
Topic #: 8

In the middle of an iteration, the product owner tells the agile team that the

government has updated legal requirements. This will result in some changes in the product

definition.

How should the project manager handle this situation?


A.

Review the iteration backlog because the product definition has changed and needs to

be reassessed before continuing the project.


B.

Continue work and ask the product owner to assess the changes and add/remove the

stories as needed in the backlog.


C.

Ask a business analyst to assess the changes and then add/remove the stories in the

backlog and prioritize them by business value.


D.

Ask the product owner to add new changes to the bottom of the backlog in order to

handle the modifications as a change request.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.