PMI Project Management Professional (2025 Version) PMP Question # 72 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 72 Topic 8 Discussion

PMP Exam Topic 8 Question 72 Discussion:
Question #: 72
Topic #: 8

An agile project is completing its second sprint and products are being finished. However, two groups with different levels of expertise disagree on the backlog priority.

What should the project manager do first to resolve this dispute?


A.

Escalate to the project sponsor to provide a solution to the conflict.


B.

Interpret the source and stage of the conflict and select a resolution approach.


C.

Apply a compromising resolution approach, involving both groups.


D.

Ask the functional managers of both groups to help find a workable solution.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.