PMI Project Management Professional (2025 Version) PMP Question # 72 Topic 8 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 72 Topic 8 Discussion

PMP Exam Topic 8 Question 72 Discussion:
Question #: 72
Topic #: 8

A project manager at a plant with continuous operations needs to deliver a project urgently to meet a market opportunity. What should the project manager do to meet the time-to-market need?


A.

Add resources to activities


B.

Conduct serial activities on tasks


C.

Increase the number of standup meetings


D.

Perform tasks in parallel


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.