PMI Project Management Professional (2025 Version) PMP Question # 57 Topic 6 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 57 Topic 6 Discussion

PMP Exam Topic 6 Question 57 Discussion:
Question #: 57
Topic #: 6

A project manager has recently joined an organization and notices that the engineering manager shouts at the project manager during project meetings Also the procurement manager will not return calls and the accountant always insists the project manager clears approved budget line items with them personally before expensing

Which three corrective actions should the project manager perform? (Choose three)


A.

Confront the people causing the stress directly with the aim of finding amicable solutions


B.

Seek support from the project management office (PMO) on addressing issues affecting the project


C.

Discuss the possible actions with the project sponsor


D.

Avoid the people causing stress and request a transfer as soon as possible


E.

Talk to the human resources (HR) manager about these concerns


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.