PMI Project Management Professional (2025 Version) PMP Question # 90 Topic 10 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 90 Topic 10 Discussion

PMP Exam Topic 10 Question 90 Discussion:
Question #: 90
Topic #: 10

A project team is completing a design, while another team in a different country is performing implementation. How should the project manager communicate the design to the implementation team?


A.

Send a detailed email with the completed design document.


B.

Conduct a workshop with all of the stakeholders.


C.

Conduct a workshop with both of the teams.


D.

Upload the design documents into the project repository.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.