PMI Project Management Professional (2025 Version) PMP Question # 88 Topic 9 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 88 Topic 9 Discussion

PMP Exam Topic 9 Question 88 Discussion:
Question #: 88
Topic #: 9

Multidisciplinary teams will be needed for a project. The project manager asks the project planner to create a consolidated schedule. The project manager determines from the consolidated schedule that the project's finish date exceeds the requested finish date.

What should the project manager suggest to the planner to analyze this issue?


A.

Verify the total float of each activity of the consolidated project schedule.


B.

Verify the critical path of the consolidated project schedule.


C.

Verify successors and predecessors of each activity of the consolidated project schedule.


D.

Verify the free float of each activity of the consolidated project schedule.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.