Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 88 Topic 9 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 88 Topic 9 Discussion

PMP Exam Topic 9 Question 88 Discussion:
Question #: 88
Topic #: 9

An organization is transitioning to an agile delivery approach. There is only one project that is being used as a pilot for the new approach. The project management office (PMO) manager has asked the project lead how communications with the project team and the stakeholders will be managed.

What should the project lead recommend?


A.

Send the weekly report to the PMO and the product owner, and use a kanban board for the project team.


B.

Send weekly reports to the PMO, and use a kanban board for the product owner and the project team.


C.

Invite the PMO manager to the daily standup with the project team and product owner.


D.

Send weekly reports to all stakeholders, including the project team and the product owner.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.