PMI Project Management Professional (2025 Version) PMP Question # 88 Topic 9 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 88 Topic 9 Discussion

PMP Exam Topic 9 Question 88 Discussion:
Question #: 88
Topic #: 9

The customer's project manager changes during the final stage of a project How can the project manager avoid a project closure delay’


A.

Update the stakeholder engagement plan


B.

Review the latest project status report and update the stakeholders


C.

Escalate the case to the customer's management team


D.

Issue the project payment invoice to the customer in advance


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.