A project sponsor is replaced during a hybrid project closure. The new project sponsor wants to change all of the project documentation to reflect a fully predictive approach.
What should the project manager do next?
A.
Review the key existing project documents with the new project sponsor.
B.
Ask the team to estimate the time it will take to update the documentation.
C.
Address the issue during the lessons learned session of the closing phase.
D.
Set up a meeting with the new project sponsor to understand their concerns.
Chosen Answer: