PMI Project Management Professional (2025 Version) PMP Question # 95 Topic 10 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 95 Topic 10 Discussion

PMP Exam Topic 10 Question 95 Discussion:
Question #: 95
Topic #: 10

A project sponsor is replaced during a hybrid project closure. The new project sponsor wants to change all of the project documentation to reflect a fully predictive approach.

What should the project manager do next?


A.

Review the key existing project documents with the new project sponsor.


B.

Ask the team to estimate the time it will take to update the documentation.


C.

Address the issue during the lessons learned session of the closing phase.


D.

Set up a meeting with the new project sponsor to understand their concerns.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.