Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 95 Topic 10 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 95 Topic 10 Discussion

PMP Exam Topic 10 Question 95 Discussion:
Question #: 95
Topic #: 10

A project manager has been working with the same group of stakeholders for 3 years using a predictive approach. The stakeholders have invested in many projects and are familiar with the approach Recently the organization has strongly encouraged all project managers to adopt an agile approach. This was announced 2 weeks before the project manager planned to kick off a large complex project with the same group of stakeholders.

What should the project manager do?


A.

Use the agile approach in the new project and schedule agile training for those stakeholders who are new to this approach


B.

Continue to use the predictive approach m the new project since it is the approach the stakeholders are familiar with using


C.

Share the pros and cons of adopting an agile approach for the new project only with the team and ask them to decide which approach to use


D.

Share and discuss the pros and cons of adopting agile with the stakeholders and choose the approach they prefer for the new project


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.