New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 95 Topic 10 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 95 Topic 10 Discussion

PMP Exam Topic 10 Question 95 Discussion:
Question #: 95
Topic #: 10

At the end of a project's initiation phase, the budget was developed and sent to the approval board. During the approval meeting, one of the key stakeholders asked how the budget was developed for future uncertainties.

How should the project manager reply?


A.

Recurrent team meetings are planned to control the budget against future uncertainties.


B.

Probabilistic analysis was used to develop the budget to address future uncertainties.


C.

The budget was developed by using the lessons learned from previous project data.


D.

Feedback from stakeholders will be addressed at each board meeting to adapt the budget.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.