Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 38 Topic 4 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 38 Topic 4 Discussion

PMP Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

A project manager has been assigned to a new project. There is one team member

who never says anything during meetings. After meetings, however, the team member sends

detailed emails with very good suggestions that help with project execution.

How should the project manager guide the team members?


A.

Review the communications management plan with the team members.


B.

Remind the team members to follow the team charter.


C.

Motivate the team members to speak freely in the meeting.


D.

Arrange a team-building activity to involve all team members.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.