PMI Project Management Professional (2025 Version) PMP Question # 38 Topic 4 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 38 Topic 4 Discussion

PMP Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

A project manager works for a large global company. The project manager is leading a project where the expected business value is to improve the company's image and reputation. During the project's closing phase, the project manager realizes that there is still a negative perception about the company's brand.

What should the project manager have done to prevent this?


A.

Monitored progress in achieving the business value throughout the project


B.

Asked for additional time to achieve the project goals and increase business value


C.

Increased the number of project resources to ensure attainment of the business value


D.

Reviewed previous projects’ lessons learned and applied them to this project


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.