Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 38 Topic 4 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 38 Topic 4 Discussion

PMP Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

An external development team is working on a large project to build a custom application for the organization. Since the requirements are not fully clear, the project

manager decides with the project sponsor to take a hybrid approach. The project manager also agrees with the vendor to fulfill minimum viable product (MVP)

requirements within the set number of sprints and to update the application according to newly identified requirements.

Which metrics should the project manager monitor and analyze?


A.

Number of completed requirements in the MVP, rejected requirements, and defects.


B.

MVP requirements completed by percentage, number of completed iterations, and number of ongoing iterations.


C.

Total number of days people worked, remaining budget of the MVP, and number of items that individuals completed.


D.

Number of allocated resources, MVP percentage of working items, and bugs.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.