PMI Project Management Professional (2025 Version) PMP Question # 38 Topic 4 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 38 Topic 4 Discussion

PMP Exam Topic 4 Question 38 Discussion:
Question #: 38
Topic #: 4

During a final investment decision meeting, all of the stakeholders were aligned on the project benefits, proposed budget, and schedule. Before final approval was given, the executive requested an aspirational target for the project team to obtain an enhanced benefit from the project.

What should the project manager do in this situation?


A.

Accept the request and commit to some benefit improvement opportunities for the project.


B.

Investigate the request and express willingness to find ways to obtain higher project benefits.


C.

Review the proposal and suggest optional benefit improvement opportunities for the project.


D.

Explain the planning and budgeting process and demonstrate that the project proposal maximizes benefits.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.