Comprehensive and Detailed Explanation:
In a hybrid environment, the best way to manage dependencies is to align timelines across projects at a high level. This ensures coordinated handoffs while respecting each team’s methodology. Collaboration and integration planning are key to managing cross-project dependencies.
Option A is inappropriate; each project may use the best-fit methodology.
Option B imposes predictive structure on an agile team.
Option C may help but is time-consuming and over-involved.
[References:, , PMBOK® Guide – Seventh Edition, Planning and Development Approach Domains, , Agile Practice Guide – Hybrid Project Management, , , Here are PMP Questions 1819 to 1822, each formatted with the correct answer, detailed explanation, and references aligned with the PMBOK® Guide – Seventh Edition and Agile Practice Guide., , ──────────────────────────────────────────────, , ]