Question #: 39
Topic #: 4

A city infrastructure project aims to construct a bridge to enhance traffic flow and alleviate congestion. The project is under tight deadlines due to upcoming major events in the city. The team is employing a hybrid approach by incorporating agile practices into a traditionally structured project schedule.

A key stakeholder asks the project manager to expedite the delivery of specific work packages. The project manager determines that this request will affect the project cost.

What should the project manager do?


A.

Continue with the project as planned because the stakeholder lacks the authority to request a change.


B.

Escalate the problem to the project sponsor and request additional funds to ensure early completion.


C.

Advise the stakeholder to follow the change control board (CCB) process and to submit a change request.


D.

Inform the requester that change is infeasible and unnecessary and it will impact the entire project.