A project manager has been assigned to a project that is in progress. The project

manager is looking for information regarding why the project is being completed.

What should the project manager do first?


A.

Evaluate the project exit criteria in the project charter.


B.

Reach out to the senior executive sponsor for the project.


C.

Understand the project success criteria and objectives.


D.

Review the project status reporting for the latest information.