PMI Project Management Professional (2025 Version) PMP Question # 4 Topic 1 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 4 Topic 1 Discussion

PMP Exam Topic 1 Question 4 Discussion:
Question #: 4
Topic #: 1

During the release of an important product, a vice president for a different product line brought a valid concern to the project team, which had to be completed before the release. The vice president has not participated in other product discussions until now. This additional work resulted in a delay of the product release.

How should the project manager have handled this situation earlier in the project?


A.

Identified the vice president as a stakeholder


B.

Recorded the vice president's concerns in the risk register


C.

Escalated any dissent to top management right away


D.

Shared project boundaries so that everyone was aware of the scope


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.