PMI Project Management Professional (2025 Version) PMP Question # 150 Topic 16 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 150 Topic 16 Discussion

PMP Exam Topic 16 Question 150 Discussion:
Question #: 150
Topic #: 16

Early on during a sprint in an agile project, the project team begins deliberating two different approaches to implement a feature. The project manager is concerned that the team is spending too much time discussing this feature, because the team needs to cover other features in the sprint as well.

How should the project manager approach the situation?


A.

Intervene in the deliberation process and weigh in on which approach would be better to use.


B.

Deliberate with the team moving the item to the product backlog and taking up the next item in the list.


C.

Stop the deliberation process and ask the team to take a vote using the nominal group technique.


D.

Allow the team to continue deliberating until the team reaches a consensus on the desired approach.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.