New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 150 Topic 16 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 150 Topic 16 Discussion

PMP Exam Topic 16 Question 150 Discussion:
Question #: 150
Topic #: 16

A project manager is managing a project to deploy new software to 200 end users. During the implementation, there is a missed process that

caused some of the users to lose their computer data.

What should the project manager do first?


A.

Meet with the team to discuss the root cause and encourage the team to take note of it and continue to focus on the deployment.


B.

Record this case until the final lessons learned session is complete to prevent impacting the team's morale during implementation.


C.

Meet with the team members and request they conduct a review of the case by providing feedback as lessons learned.


D.

Invite a consultant to review the process in order not to repeat the same issue and share the results with the team.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.