New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 41 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 41 Topic 5 Discussion

PMP Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

A project manager is working on an ongoing construction project. The designer notifies the project manager about materials that were not included in the budget due to a technical mistake.

What should the project manager have done to avoid this situation?


A.

Asked the project sponsor to review the budget


B.

Updated the budget before moving to another stage of the project


C.

Added enough budget to cover all uncertainties


D.

Used past projects as a reference during budget estimations


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.