PMI Project Management Professional (2025 Version) PMP Question # 41 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 41 Topic 5 Discussion

PMP Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

A project team has experienced deliverable delays in the last few iterations. During the retrospective, the team realizes that the quality issues identified are because the quality process is outdated.

Who should the project manager ask to update the process?


A.

Project team


B.

Project management office (PMO)


C.

Quality lead


D.

Product owner


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.