PMI Project Management Professional (2025 Version) PMP Question # 41 Topic 5 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 41 Topic 5 Discussion

PMP Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

A project manager for a factory construction project in a small town is evaluating the necessary actions to engage stakeholders The local community is speculating the impact of the facility. There are rumors of job opportunities and environmental impacts which are listed on the project risk matrix

What should the project manager do with regard to community engagement in this situation''


A.

Include the local union representative in the high-power, high-impact stakeholder group


B.

Focus on the sideward stakeholders only and let the organization manage the community.


C.

Build channels to extend communication efforts to the local community


D.

Use the city administration to address communication with the community


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.