Summer Certification Special Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: force70

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 41 Topic 5 Discussion

PMI Project Management Professional (PMP) July 2026 Update PMP Question # 41 Topic 5 Discussion

PMP Exam Topic 5 Question 41 Discussion:
Question #: 41
Topic #: 5

A project team had been developing their deliverables on a 2-week sprint. The deliverables were tested and proven to be functional. However, during the sprint

review, they were rejected because they failed to meet the end-user requirements.

What actions should the project manager have done?


A.

Rotated product owner role among the team to have brought in fresh perspectives during sprint planning.


B.

Included the project sponsor ' s requirements in the user stories during the sprint planning.


C.

Refined user personas with stakeholder input and ensured the team had used them to interpret the stories.


D.

Conducted additional tests and increased the definition of done criteria to have included stakeholder approval.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.