New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 107 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 107 Topic 11 Discussion

PMP Exam Topic 11 Question 107 Discussion:
Question #: 107
Topic #: 11

A project manager is leading a project team composed of members with varying levels of knowledge and

experience. Some are experts and some have less than 1 year of experience. The project schedule was approved by the steering committee.

What should the project manager do?


A.

Ask the less-experienced members to perform tasks exactly as they are instructed by the experienced members.


B.

Ask each experienced member to be the mentor to one of the less-experienced members.


C.

Ask the more experienced members to review all of the tasks performed by the less-experienced members.


D.

Ask the resource manager to replace the less-experienced members with more experienced team members.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.