PMI Project Management Professional (2025 Version) PMP Question # 111 Topic 12 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 111 Topic 12 Discussion

PMP Exam Topic 12 Question 111 Discussion:
Question #: 111
Topic #: 12

Stakeholders in some industries prefer to deal with programmers and system analysts directly, bypassing project managers. This complicates managing resources on projects

How should a project manager solve this issue?


A.

Propose implementing a new project management information system (PMIS).


B.

Request a meeting with senior management to escalate the situation


C.

Promote adoption of the communications management plan with the project team.


D.

Host a team-building event to develop team cohesion and improve communication


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.