PMI Project Management Professional (2025 Version) PMP Question # 111 Topic 12 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 111 Topic 12 Discussion

PMP Exam Topic 12 Question 111 Discussion:
Question #: 111
Topic #: 12

A project team has difficulty understanding the relationship between functional requirements and their associated benefit to the business stakeholders.

How should the project manager improve the team's understanding?


A.

Involve team members in stakeholder analysis and engagement.


B.

Invite all stakeholders to progress meetings to avoid ambiguity.


C.

Ensure team members have access to a well-written requirements traceability matrix.


D.

Engage with the project sponsor and ensure the product backlog is correct and up to date.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.