PMI Project Management Professional (2025 Version) PMP Question # 110 Topic 12 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 110 Topic 12 Discussion

PMP Exam Topic 12 Question 110 Discussion:
Question #: 110
Topic #: 12

In the past year, a company paid US$60,000 to an external subcontractor for an ongoing project. The project manager has been asked to

evaluate if the project can be delivered more cost effectively this year by using internal labor. The project manager used an optimistic term of 4

months, a pessimistic term of 6 months, and a most expected term of 5 months, and has concluded that the service can be delivered with the

following resources:

* Two engineers (monthly salary of US$700 each)

* One project manager (monthly salary of US$1,600)

* Additional estimated monthly expenses of US$2,000

The project manager used the program evaluation and review technique (PERT) to calculate the savings if the project is delivered with in-house

resources.

How much money will the project manager estimate the company can save?


A.

US$35,000


B.

US$20,000


C.

US$40,000


D.

US$30,000


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.