PMI Project Management Professional (2025 Version) PMP Question # 105 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 105 Topic 11 Discussion

PMP Exam Topic 11 Question 105 Discussion:
Question #: 105
Topic #: 11

The project velocity has recently slipped, and a decision was made to skip testing to increase the momentum and bong the project back on track What will the project manager need to focus on as a result of this decision?


A.

Increased bum rate


B.

Increased cost


C.

Increased technical debt


D.

Decreased efficiency


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.