New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 105 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 105 Topic 11 Discussion

PMP Exam Topic 11 Question 105 Discussion:
Question #: 105
Topic #: 11

A customer is concerned about the time required to complete a project and is asking the project team to reduce the number of iterations required to complete the product. Which approach should the project manager take?


A.

Ask the team to raise blockers or impediments in daily meetings.


B.

Prioritize deliverables based on business value and define frequent releases.


C.

Ask the team to challenge the project estimations for a faster delivery.


D.

Prioritize the tasks with high risks to reduce the number of iterations required.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.