PMI Project Management Professional (2025 Version) PMP Question # 105 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 105 Topic 11 Discussion

PMP Exam Topic 11 Question 105 Discussion:
Question #: 105
Topic #: 11

A project manager assigned to an education project needs to train a workforce in application development. The customer is responsible for

providing the training center, and the deadline to start the first training is in 2 weeks. The customer calls to say that the center will not be available

in 2 weeks due to some unforeseen problems.

What should the project manager do next?


A.

Apply the terms and conditions of the contract with penalties.


B.

Issue a change request to reflect the anticipated date for training.


C.

Help the customer find an alternative location to start the training.


D.

Update the project schedule with the new date for training.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.