PMI Project Management Professional (2025 Version) PMP Question # 104 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 104 Topic 11 Discussion

PMP Exam Topic 11 Question 104 Discussion:
Question #: 104
Topic #: 11

A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?


A.

Reject the changes as the lead time is too short.


B.

Determine whether the project team is capable of making the changes.


C.

Review the additional changes and perform integrated change control.


D.

Check if the changes are covered in the statement of work (SOW).


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.