PMI Project Management Professional (2025 Version) PMP Question # 104 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 104 Topic 11 Discussion

PMP Exam Topic 11 Question 104 Discussion:
Question #: 104
Topic #: 11

A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?


A.

Perform a risk assessment and define a risk response action plan.


B.

Proceed with the project using management reserves to cover any delays or losses.


C.

Propose a pause in this phase to save labor costs and asset depreciation.


D.

Establish new partnerships with other suppliers in anticipation of any delays.