New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 104 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 104 Topic 11 Discussion

PMP Exam Topic 11 Question 104 Discussion:
Question #: 104
Topic #: 11

A project is ending its fifth out of six iterations. During the iteration review, a customer adds a new regulatory feature that exceeds the capacity of the remaining iteration.

What should the project lead do?


A.

Register an issue and escalate it to the project sponsor.


B.

Invite the stakeholders to discuss a new prioritization.


C.

Estimate the management to replace the customer service manager.


D.

Increase the team capacity to finish the project on time.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.