PMI Project Management Professional (2025 Version) PMP Question # 103 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 103 Topic 11 Discussion

PMP Exam Topic 11 Question 103 Discussion:
Question #: 103
Topic #: 11

Presented with flowcharts of the organization's operations, stakeholders are unfamiliar with several recorded processes, and others note that some recorded processes were discontinued. The project sponsor notices that the chart is several years old and wants an updated version immediately.

What should the project manager do?


A.

Assemble the entire project team to produce new flowcharts from current versions.


B.

Assemble and create teams of experts and stakeholders to update flowcharts to reflect current conditions.


C.

Raise a change request and ask the project sponsor to approve it so the flowcharts can be updated.


D.

Work with a consultant and the project sponsor to produce new flowcharts.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.