New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 128 Topic 13 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 128 Topic 13 Discussion

PMP Exam Topic 13 Question 128 Discussion:
Question #: 128
Topic #: 13

Companies A and B are codeveloping a cutting-edge technology product. Based on customer feedback, the marketing department urgently requests a new feature in 2 weeks. Company A's front end is ready, but company B requires 4 weeks to deliver the complete back end and is busy with the current release.

What should the project manager do to obtain agreement from both companies and acceptance from marketing?


A.

Create a special release 4 weeks after the current release to deliver the new feature in its entirety.


B.

Stop the current release work for 4 weeks in order to work and deliver the new feature completely.


C.

Plan the delivery of a minimum viable feature in 2 weeks to enable early showcasing of business value.


D.

Add the new feature to the list for the next release and continue working on the current release.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.