PMI Project Management Professional (2025 Version) PMP Question # 128 Topic 13 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 128 Topic 13 Discussion

PMP Exam Topic 13 Question 128 Discussion:
Question #: 128
Topic #: 13

A company hired a new project lead to incorporate some agile practices.

Which three changes should the project lead incorporate in the existing team meetings? (Choose 3)


A.

Add sprints and sprint reviews as necessary.


B.

Agree with the team on some ground rules.


C.

Avoid extended discussions during daily meetings.


D.

Select a team member to lead the daily meetings.


E.

Encourage everyone to participate in the daily meetings.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.