New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 112 Topic 12 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 112 Topic 12 Discussion

PMP Exam Topic 12 Question 112 Discussion:
Question #: 112
Topic #: 12

A project manager is leading a hybrid project. The only available resources that have experience with agile are not at the project manager's location. The project has a strict

schedule and budget, and the project manager is concerned about their ability to deliver it.

What should the project manager do?


A.

Request a budget extension to get local resources experienced in agile.


B.

Plan to have the agile resources temporarily relocate to the project manager's location.


C.

Engage the agile resources through video conferencing on a daily basis.


D.

Advise the sponsor that the project will be delayed as agile training will be required.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.