PMI Project Management Professional (2025 Version) PMP Question # 112 Topic 12 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 112 Topic 12 Discussion

PMP Exam Topic 12 Question 112 Discussion:
Question #: 112
Topic #: 12

A new resource has joined an iterative project team The project manager notices that the resource is unable to complete the deliverables on time

How should the project manager address this situation?


A.

Address the lack of performance by coaching the new team member


B.

Discuss options to improve performance with the resource manager


C.

Provide performance feedback as part of the retrospective ceremony.


D.

Request a more efficient replacement resource from the project sponsor


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.