PMI Project Management Professional (2025 Version) PMP Question # 67 Topic 7 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 67 Topic 7 Discussion

PMP Exam Topic 7 Question 67 Discussion:
Question #: 67
Topic #: 7

A new project manager has been assigned to a project that is in its second phase The product created in the first phase was transferred to operations During a meeting, the project sponsor complained that some of the reports contain conflicting data on the product value

What should the new project manager do next?


A.

Review the benefits management plan


B.

Refer to the lessons learned from the first phase


C.

Consult the project reports from the previous project manager


D.

Collect information from related departments


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.