PMI Project Management Professional (2025 Version) PMP Question # 109 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 109 Topic 11 Discussion

PMP Exam Topic 11 Question 109 Discussion:
Question #: 109
Topic #: 11

During a project planning meeting, a product manager and team are finalizing the project deliverables and notice that a key feature has a dependency from another team. A team member suggests removing the feature from the scope.

What should the project manager do?


A.

Advise the team not to reduce the scope of the feature because the product manager originally included that requirement.


B.

Discuss the issue with the team so the product manager can understand the trade-offs.


C.

Suggest the team and product manager go with the faster approach, reducing the scope.


D.

Prepare a presentation for the project sponsor with the team that includes both solutions and seek the sponsor's guidance.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.