New Year Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 109 Topic 11 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 109 Topic 11 Discussion

PMP Exam Topic 11 Question 109 Discussion:
Question #: 109
Topic #: 11

During a project meeting, the project manager expressed the importance of delivering reports on time. These individual reports will be

consolidated into a single report. One of the team member's reports was not delivered on time and therefore the report could not be integrated

with the other reports. This demonstrates a lack of teamwork and impacts project success.

What should the project manager do to resolve this issue?


A.

Assign the task to someone else on the team.


B.

Discuss it with the team member in confidence.


C.

Discuss this matter during the project meeting.


D.

Include this item in the risk register.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.