A project manager is working on a software development project. The project manager and the project team identified the project risks. As the
project progressed, one of the risks materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk was closed.
At what point did the project manager move the risk from the risk register to the issue log?
A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle.
What should the project manager do next?
The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team
Which two actions should the project manager take? (Choose two)
A project manager is reviewing the team's Kanban board for an iteration with 16 tasks in progress. All the tasks are equally sized with an estimate of 8 man-hours of effort needed to complete each task. The team is made up of five cross-functional members. The normal working calendar is 8 hours per day; however, two of the team members will only work at 50% capacity. The project manager has a maximum of one week to deliver these tasks in progress due to government regulations.
Will the project manager meet this objective?
A project team needs to create artifacts for an upcoming steering committee.
What should the project manager do first?
A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.
What should the project manager use to explain the project scope?
A flagship project is sponsored by the CEO and has a critical go-live date. The project's product requires a regulatory review and approval before it can go live. The CEO instructed to allow only 2 weeks for regulatory approval in the schedule; however, the director for the regulatory liaison indicated 6 weeks was a more realistic timeline.
What should the project manager do?
A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped
How should the project manager handle the situation?
A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.
What should the project manager do next ?
At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried
to contact the consultant but has been told that the consultant does not have the time to discuss the project.
What should the project manager do to move the project forward?
An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing
the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.
What should the project manager do?
A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment. The project manager started communication with the team to move the project forward
What should the project manager do first at this pomp
A hybrid project team is working on an upgraded version of software for their
product owner. The team is also responsible for supporting the existing product and
customers. For the last three sprints, the team had to stop their project work and focus on
major support items for the product owner. The testers are struggling to cope with the
constant changes to the plan, which has resulted in a number of emotional outbursts.
How should the project manager proceed?
A project team has been together for a long time and has been led by three different
project managers. Lately, the performance of one of the team members has been declining
and has affected the project delivery.
What should the current project manager do to ensure that team performance is improved and
sustained?
During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?
A project manager who works for a company involved in several industries is asked
to lead a software development project for a government agency. The company attempted to
execute similar projects for other industries before but was unsuccessful.
What should the project manager do to ensure project success?
A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late. Digress into solutioning. or skip the meetings altogether.
How should the project manager improve this situation with the project team?
A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.
What should the project manager do to address the concem9
A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed
To what type of communication is the team member referring?
A project team is facing challenges understanding how to deliver a project's scope.
A senior subject matter expert (SME) from the organization's global office is in town for 1 week.
What should the project manager do to benefit from the SME's presence?
A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule
What should the project manager do?
In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet
What should the project team have done to avoid this issue?
The project manager realizes that the product owner has a lot of potential but is lacking communication skills. How should the project manager help the product owner to develop these skills while executing the project?
An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives
What should the project manager do?
A new project manager is managing a hybrid project. The project manager wants to be
a servant leader to support the team by removing impediments but is not receiving feedback
from the team about the issues and risks they are facing.
What should the project manager do?
A newly appointed product owner is working with a project team that is using agile
for the first time. The product owner is constantly disrupting various team members throughout
the day to discuss progress. This has resulted in the team feeling micromanaged and
frustrated because of the constant disruptions.
How should the project manager proceed?
A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.
What should the project manager do?
A developer who has almost completed a required product feature for a prototype
leaves the company in the middle of an iteration. What should the project manager do?
A project manager is assigned to a new water treatment plant project that has been
delayed for many years. It is revealed in the project charter that the sponsors of this project
are from three different business units. This is the first time the sponsors have ever
implemented such a project.
What should the project manager do?
A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.
What should the project manager ask the team to do?
A project manager is leading an integration project for a retail company. The project
demands a lot of time from the stakeholders to make important business decisions. The
project is critical and must be completed on time and within budget.
What should the project manager do to ensure that key stakeholders are available for this
project?
A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?
A project leader is assigned to a new project and is asked to assemble an effective
five-member agile team. If the project leader has no restrictions, which team should they
choose?
A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person
What should the project manager do first?
During the early phases of a project, mitigation actions were not executed in a
timely manner; therefore, the project schedule was impacted. Several project stakeholders are
now frustrated with the delays.
What should the project manager have done to manage the issue?
A business improvement opportunity to reduce energy usage has been identified.
The project manager has assembled a team that includes site engineers to deliver this project.
However, due to production imperatives, the site engineers may not be fully focused on the
project.
How should the project manager manage the team?
As a project is reaching completion, the project sponsor tells the project manager to
immediately close the project and to move on to another project. Which critical task should the
project manager complete before closing the project?
During the execution of a construction project, the project sponsor asks to make
changes to the floor plan by adding a minimal storage room. The sponsor insists on making
this last-minute change, but they would like to avoid delays to the project.
Which document should the project manager refer to first?
A project manager receives a serious complaint from a functional manager about a
team member. What should the project manager do?
One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.
What should the project manager do?
A project with multiple teams recently transitioned from a predictive approach to agile
as requested by the product owner. Midway through implementation, a team member noticed
there was no technical capability to support the current business requirement; therefore, the
project will need to be reworked and the issue needs to be communicated to all stakeholders.
What should the agile project lead have done to avoid this situation?
During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.
What should the project manager do first?
A project manager is working on a project with multiple workstreams. One of the
workstreams missed its deadline multiple times.
Who should the project manager speak to about this situation to ensure it does not happen
again?
During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?
An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.
What tools should the agile project manager use to do these estimates?
A project manager is working on a large project in another country and realizes that
only a few people from the project team are working on all of the releases. What should the
project manager do to prevent this in the future?
A project manager is establishing a project management office (PMO) for a
company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.
Which activity should the project manager use to help train the stakeholders?
After difficult negotiations, a customer committed to pay the cost for changes to the
project scope. The team seems unhappy as the project completion time will take longer than
previously scheduled.
How should the project manager support the outcome of the new agreement?
A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.
What should the project manager do next?
A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.
What should the project manager do?