Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 6 out of 12 pages
Viewing questions 251-300 out of questions
Questions # 251:

A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.

What should the project manager do first?

Options:

A.

Update the project charter with the new requirement.


B.

Add a risk to the risk register.


C.

Add it to the issue log as an ongoing issue.


D.

Review and validate the scope management plan.


Expert Solution
Questions # 252:

A project manager is leading a project that will be delivered using a Scrum framework. The organization has an innovative project management office (PMO) that fully supports agile and also has a very friendly procurement team. A new vendor needs to be engaged to provide more developers for a new reporting platform.

What should the project manager do?

Options:

A.

Use an agile approach and engage a vendor that delivered well in a previous organization.


B.

Consult the product owner and engage a vendor that is recommended by them.


C.

Consult the development team and engage a vendor that is recommended by them.


D.

Use a formal approach using procurement policies, procedures, forms, and work instructions.


Expert Solution
Questions # 253:

A project manager has been assigned to a project where the budget is very tight. Incurring extra costs is not an option.

What should the project manager do to manage this situation?

Options:

A.

File a change request to make the customer billable for all extra costs incurred for the project.


B.

Ask the accounting department to forward all project expenses to the project manager's email.


C.

Monitor the budget for the project continually and anticipate any issues if possible.


D.

Ask the project resources to finish their assignments in less time than originally planned.


Expert Solution
Questions # 254:

A project manager is working on a project to release a new version of a key product, The product strategy and marketing areas are still working on defining the final details for the products appearance, but the team is clear about the main features. During the last sprint review, the project sponser expressed concerns about the low quality of the product,

What should the project manager, as a servant leader, do to address this situation?

Options:

A.

Dedicate the next sprint to completing the missing details.


B.

Apply fast-track techniques to work on the missing details in parallel,


C.

Continue iterating and monitoring quality aspects sprint by sprint.


D.

Create a new risk entry for the delay in the risk management plan.


Expert Solution
Questions # 255:

During a system demo, a project stakeholder rejects the features completed from the most recent user stories. According to the stakeholder, the product does not meet the

quality standards required by regulations.

What should the project manager have done to avoid this?

Options:

A.

Reviewed with the product owner that all the stories worked on in the iteration were in the project backlog


B.

Ensured that the project sponsor understood the scope of the project to avoid any future complaints


C.

Reviewed with the product owner that all acceptance criteria were met for the stories worked on in the iteration


D.

Ensured the stakeholder concerns were properly addressed in the iteration to avoid future setbacks


Expert Solution
Questions # 256:

During the third iteration of a project, the product owner requests another mandatory feature. This also happened in the previous two sprints, which resulted in failure and caused frustration within the team.

What should the project manager do next?

Options:

A.

Incorporate the changes in the last sprint before the first release.


B.

Call for an internal meeting to discuss the changes and their value.


C.

Ask the product owner to prioritize the backlog with the project team.


D.

Request the scrum team to prioritize the product backlog.


Expert Solution
Questions # 257:

A project manager is assigned to a project team midway through execution. Several dependencies are impacting the project, and the project manager feels the team is not adequately informed of the impacting changes.

What should the project manager do first?

Options:

A.

Convene an impact analysis meeting.


B.

Escalate the issue to the product owner.


C.

Consult the communications management plan.


D.

Review the stakeholder register.


Expert Solution
Questions # 258:

A project manager is newly appointed to an ongoing project that will develop a new solution using an affiliate of the company. The deploying

resources will come from another entity of the company. When asked to confirm the availability of the deploying team, the deploying manager declined.

What should the project manager do first?

Options:

A.

Reschedule the project taking this new information into account.


B.

Refer to the project's resource management plan.


C.

Ask the project sponsor for external resources.


D.

Create a change request to be validated by the project sponsor.


Expert Solution
Questions # 259:

During the execution of a hybrid project, one developer had to be replaced. The new resource is extremely competent in quality assurance tasks, but does not have much

experience in development.

What should the project manager do?

Options:

A.

Allow the team to reevaluate the tasks and determine how they should be allocated.


B.

Maintain the same task allocation structure to avoid any disruption in the project team.


C.

Move the developer to another team and look for a replacement developer.


D.

Request that all quality assurance tasks be allocated to the new resource.


Expert Solution
Questions # 260:

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?

Options:

A.

Update the project management plan and adjust the project budget with this change request.


B.

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.


C.

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.


D.

Request a meeting with the stakeholders and their team members to inform them about this change.


Expert Solution
Questions # 261:

During the execution phase of a healthcare IT project, the project manager finds one stakeholder is very difficult to communicate with and obtain

feedback from on project deliverables. What should the project manager do?

Options:

A.

Share a template with the stakeholder to receive feedback on deliverables.


B.

Ask the project sponsor to arrange a meeting with the stakeholder.


C.

Use networking skills to approach the stakeholder.


D.

Update the stakeholder engagement plan for the stakeholder.


Expert Solution
Questions # 262:

A new team member joins an agile team. In a previous role, this team member was a subject matter expert (SME). This team member often directs the team on how to solve problems based on previous experience.

What should the project manager do first?

Options:

A.

Update the definition of done (DoD) to include a review by the new team member to ensure the best outcome of each deliverable.


B.

Ask the new team member to create a wiki that the rest of the team can reference in the future for all questions.


C.

Ask the new team member to size all the stories in the backlog so that the rest of the team can focus on delivery.


D.

Let the new team member know that even if they know the answer, it is better to give the team a chance to solve their own problems


Expert Solution
Questions # 263:

A project manager is in the middle of handling a major upgrade to an existing product. The project manager learns that the resources initially promised as part of the project are being moved to another priority project.

What should the project manager do?

Options:

A.

Retrieve the documentation that shows the resource allocation.


B.

Examine ways of modifying the scope of the project.


C.

Adopt a resource leveling procedure to level the resources.


D.

Perform an impact analysis to see the effect on the project.


Expert Solution
Questions # 264:

A project manager is assigned to a project that is in the execution phase that has different types of stakeholders. Some of the stakeholders are very interested in the project, whereas other do not show the same level of interest.

What should the project manager do to assure the project finishes correctly?

Options:

A.

Look at the stakeholder assessment matrix to find stakeholders' interests and make updates if necessary.


B.

Invite the most interested stakeholders to risk assessment sessions and assure the less interested stakeholders agree with the requirements.


C.

Review the user person definitions to find the interests of the stakeholders and make updates if necessary.


D.

Create a stakeholder assessment plan to manage stakeholder engagement and took at stakeholders' approvals.


Expert Solution
Questions # 265:

Midway into a project, the project manager is concerned with the lack of responsiveness from a vendor. What should the project manager do to

ensure the project is delivered successfully?

Options:

A.

Ask the vendor to communicate via the established channels.


B.

Invite the vendor to a meeting to discuss the concerns.


C.

Escalate the vendor's lack of responsiveness to the project sponsor.


D.

Proceed with other tasks while awaiting a response from the vendor.


Expert Solution
Questions # 266:

A project manager's customer is new to agile approaches. When the customer found out that the project was going to use an agile approach, the customer became

concerned that the product quality will be sacrificed.

What should the project manager do?

Options:

A.

Ensure that the customer and the delivery team agree on the definition of done (DoD) in the beginning of the project.


B.

Invite the customer to join the daily standup meetings to better understand the product design and progress.


C.

Ensure the team demonstrates product features to this customer regularly to collect feedback and improve as needed.


D.

Invite the customer to join the regular sprint planning sessions to better understand the project's progress.


Expert Solution
Questions # 267:

A team is working on a project with three iterations. The project manager is reviewing the burndown chart What is the point where the chart shows that the team is performing below the plan?

Question # 267


Expert Solution
Questions # 268:

A project manager is working in a company that has several global offices. During resource planning for a new project, the project manager realizes that the company requires projects to include team members from different continents.

What should the project manager do to ensure a successful project execution?

Options:

A.

invite all resources to the project manager's location to form a cohesive team until all deliverables are completed,


B.

Send emails with information about the project deliverables on the first day of the project.


C.

Connect with every location and check their preferred methods of communication.


D.

Plan for a meeting with the project sponsor to discuss the possibility of utilizing only local colleagues.


Expert Solution
Questions # 269:

A project manager has recently moved to an organization to lead a key project. The project manager notices that team performance is below the target, and the tasks assigned are not delivered on time. Team commitment is also not as appropriate as it should be.

What should the project manager do?

Options:

A.

Study and determine the appropriate leadership style suitable for the team.


B.

Hire a project team leader who can influence the project team members.


C.

Schedule a meeting and communicate the performance concern to the team.


D.

Apply an agile approach to help improve team performance.


Expert Solution
Questions # 270:

In an agile project, some stakeholders are asking to have a meeting with the team every 2 weeks in order to understand project progress. What

should the project lead do next?

Options:

A.

Invite the stakeholders to the retrospective meetings.


B.

Invite the stakeholders to the sprint review meetings.


C.

Hold a meeting every 2 weeks with the stakeholders.


D.

Negotiate by sending an informative email to stakeholders.


Expert Solution
Questions # 271:

A project manager manages multiple information technology (IT) projects in a matrix organization. The project manager schedules a meeting with one of the functional

managers to coordinate testing support for two software development projects. Unfortunately, the functional manager is not able to attend the meeting and informs the project manager that there may not be any resources available to test the software.

What should the project manager do?

Options:

A.

Discuss the testing requirements with a test engineer and negotiate the best approach to test the newly developed software.


B.

Meet with the project team to collaboratively determine how the project manager can ensure the needed testing assistance is obtained.


C.

Request a meeting with the sponsor to change the scope to allow the development team to conduct testing.


D.

Meet with a procurement specialist to negotiate with a company that specializes in software testing to test the software.


Expert Solution
Questions # 272:

Halfway through a project, the project sponsor is replaced by another peer who was not previously engaged in the project. The new project sponsor has rejected most of the project artifacts, and the team did not get the latest increment approved on the current iteration. Stakeholders are not feeling confident about the project outcome.

What should the project manager have done to prevent this situation?

Options:

A.

Performed a stakeholder analysis when the sponsor joined the project


B.

Held a governance meeting to review the project increment


C.

Conducted a product iteration review with the new project sponsor


D.

Escalated the issue to ensure the increment would be approved


Expert Solution
Questions # 273:

After assigning tasks to a project team, a project manager discovers that some team members are uncomfortable. Same team members are having 4 difficult time understanding their assigned tasks, whereas other team members are challenging the schedule based on that allocation to the project.

Which phase of the Tuckman ladder of team formation is occurring?

Options:

A.

Forming


B.

Mourning


C.

Storming


D.

Norming


Expert Solution
Questions # 274:

A product owner is invited to a sprint review meeting. At the end of the review, the product owner says that the increment is ready to be delivered to the customer.

What conclusion should the project manager come to with regard to the product owner's statement?

Options:

A.

The product owner does not have visibility into what the team has done in the product increment.


B.

The product owner trusts the team and is marking the product as complete.


C.

The product owner has evaluated the product against the definition of done (DoD).


D.

The product owner will release the product to customers without showing them a demo.


Expert Solution
Questions # 275:

At the end of a workshop to review project deliverables, a number of follow-up action items were generated. What should the project manager do next?

Options:

A.

Defer all actions until the next workshop to keep the team focused on other higher priorities


B.

Follow up on each item as soon as possible to ensure timely completion and report the status to management.


C.

Review the critical path and update the project schedule with the newly identified tasks.


D.

Prioritize the actions with the team, assign individuals who will be responsible for completion, and monitor progress.


Expert Solution
Questions # 276:

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?

Options:

A.

Adopt the same timeframe as the closed project for the current project.


B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.


C.

Create a draft schedule based on the activity list and the historical data from the closed project.


D.

Evaluate each activity duration and build a new project schedule.


Expert Solution
Questions # 277:

An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing

the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.

What should the project manager do?

Options:

A.

Recommend splitting the project into two smaller projects in order to work exclusively in an agile environment without interference from a predictive approach.


B.

Propose that the well-defined scope items be delivered using a predictive approach and use an agile approach to deal with the complex

items.


C.

Maintain stakeholder momentum in working on the scope definition until a full detailed scope is achieved prior to starting the project.


D.

Update the risk register and escalate the issue to the project management office (PMO), requesting more resources be added to help define

the project scope.


Expert Solution
Questions # 278:

A key customer stakeholder asks the project team to include new tasks in the backlog and begin analyzing new requests. The customer expects results as soon as possible and pressures the team to attend noncritical meetings. The team is frustrated by this situation.

How should the project manager approach this situation?

Options:

A.

Understand the customer's perspective and provide mentoring on agile mindsets.


B.

Call for an internal team retrospective and create an improvement action plan.


C.

Ask the customer to work with the product owner to prioritize all requests.


D.

Work with the team to receive customer directions and improve the process.


Expert Solution
Questions # 279:

A senior employee with experience relevant to a highly complex project is seeking a promotion to be able to join the project. The employee has made a recommendation regarding the project. The project charter was recently approved.

How should the project manager address the employee's request?

Options:

A.

Evaluate the employee's recommendation by reviewing the lessons learned from a similar project.


B.

Create a salience model to determine if the employee will have influence on the project.


C.

Ask the project sponsor to revisit the project charter to consider the employee's recommendation.


D.

Assess the influence and power of the employee to see if the employee will add value.


Expert Solution
Questions # 280:

A newly assigned project manager is reviewing the project management plan and realizes that the project is running behind schedule. What should the new project manager

do to address this situation?

Options:

A.

Modify the project management plan and get approval from relevant stakeholders


B.

Add more resources to recover the schedule without making changes to the baseline.


C.

Issue a change order to the change control board (CCB) and rebaseline the schedule.


D.

Negotiate with the project sponsor immediately and establish a new project charter.


Expert Solution
Questions # 281:

During the project planning phase, a project manager is informed that they cannot start one activity before another department implements the

required IT system. What should the project manager do?

Options:

A.

Fast track this dependency to avoid delaying the project.


B.

Perform Integrated Change Control.


C.

Include the dependency in the project schedule.


D.

Ask IT to prioritize the needed system to meet the schedule.


Expert Solution
Questions # 282:

A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does

not have a requirement for it.

What should the project manager do?

Options:

A.

Ask the team to collect the knowledge locally and share it at the end of the project.


B.

Utilize the cloud wiki to collect the necessary knowledge.


C.

Coordinate with the team and the project stakeholders to collect the knowledge.


D.

Provide just-in-time knowledge to the client, upon request.


Expert Solution
Questions # 283:

A company wants to be a pioneer in its industry and has announced the launch date of a new innovative product. After the first sprint planning, the

team realizes that it is not possible to deliver all the features in the required time.

What should the project manager do to ensure success?

Options:

A.

Increase the capacity of the team to deliver the completed backlog on time.


B.

Ask the customer to reduce the backlog to meet the launch date.


C.

Assist the team in defining a minimum viable product (MVP) by the launch date.


D.

Schedule a meeting with the stakeholders to review the contingency plan.


Expert Solution
Questions # 284:

A project manager just completed the planning phase when a new stakeholder was assigned to the project. The deliverables were discussed with the customer, but the new stakeholder is still concerned about the benefits of two of the deliverables.

What should the project manager do next to address this stakeholder’s concerns?

Options:

A.

Review the benefits realization plan with the stakeholder.


B.

Provide the stakeholder with regular updates on project progress.


C.

Add the stakeholder to the stakeholder engagement plan.


D.

Review the prior analysis results with the stakeholder.


Expert Solution
Questions # 285:

A project manager is working for an organization in country A and has been tasked with opening the first brick-and-mortar store in country B. The sponsor has identified the city for the store and wants to minimize any potential issues with the local government.

Which action should the project manager take to address the sponsor's request?

Options:

A.

Work with the organization's real estate department and reach out to the local government to identify the best location for the store.


B.

Work with the local government to build the profiles of employees that will be working in the store.


C.

Work with the organization's legal department to identify local regulations to ensure project compliance.


D.

Work with the organization's project management office (PMO) to build a project team of residents located in the city.


Expert Solution
Questions # 286:

A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings,

the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level.

How should the project manager ensure that project risks are reported accurately in the risk register?

Options:

A.

Review the risks throughout project execution.


B.

Plan to update the risks at project closure.


C.

Update the risks in the risk management plan.


D.

List the project risks identified in the kick-off meeting.


Expert Solution
Questions # 287:

A project manager is working on a time and materials (T&M) project using a hybrid approach. The milestones and outcomes are defined for the first 6 months with

incremental releases every month. After the first 2 months, the client communicates their dissatisfaction with the results and asks to change the course of the project. The project manager held a face-to-face meeting with the client and now has a better understanding of the newly desired milestones and outcomes.

What should the project manager do first?

Options:

A.

Forward the client's request to management as a change request to get formal approval.


B.

Document the information in the meeting minutes and share it with the project stakeholders.


C.

Draft a contract change with the desired scope changes and send it to the client for approval.


D.

Finish the current monthly release as it was planned and replan for the future months.


Expert Solution
Questions # 288:

A key team member informs the project manager that they have been accepted to a master’s degree program. The team member explains that the first semester of the master's program will coincide with the last phase of the project.

What should the project manager do?

Options:

A.

Ask the team member to delegate some of their tasks to another colleague during the last phase of the project.


B.

Suggest the team member postpone their enrollment in the master's program until the project is completed.


C.

Ask the team member to inform human resources (HR) about their enrollment in the master's program.


D.

Assess the team member's commitment to the master's program and its impact on project performance.


Expert Solution
Questions # 289:

A project manager has been assigned to a new digital product line, which the company hopes will boost their revenue. The product is complex and requires customer feedback to continually refine the product. The project is being handled by a cross-functional agile team.

What should the project manager do to ensure value is delivered quickly?

Options:

A.

Plan the project to deliver value incrementally with regular releases.


B.

Request a budget increase to pay the subject matter experts (SMEs) more overtime


C.

Identify tasks that can run in parallel to deliver the project faster.


D.

Ask the project sponsor to provide additional resources to fast track the project.


Expert Solution
Questions # 290:

After an executive-level reorganization, the new project sponsor is not keen on continuing with the project. What should the project manager do?

Options:

A.

Ask management to replace the new sponsor with the previous sponsor.


B.

Request the previous sponsor to discuss changes with the project team.


C.

Explore ways to share the project vision and outcome with the new sponsor.


D.

Find ways to bypass the new sponsor and reach management for support.


Expert Solution
Questions # 291:

The first task a project manager needs to complete on a new project is improving stakeholder engagement. How should the project manager complete the power/interest grid based on the following scenario:

• The marketing director is the key stakeholder. as the project will create a new product for the company.

• The finance director is providing funding and does not have much time to follow the tracking of the project.

• The sales representatives assigned to the team provided some negative feedback on the requirements

• The human resources (HR) intern assigned to the team was satisfied with the new product interlace.

Question # 291


Expert Solution
Questions # 292:

An experienced project team member always points out the issues of other team members during meetings. The other team members feel that

the experienced team member is deflecting their own issues in meetings.

What should the project manager do?

Options:

A.

Arrange separated group meetings to allow everyone to express their opinions.


B.

Review the communications management plan with the team and enforce its implementation.


C.

Prepare an agenda for all future team meetings and facilitate the discussion.


D.

Speak with the experienced team member to discuss the issues in a supportive way.


Expert Solution
Questions # 293:

A major issue about conflicting priorities has been highlighted by the project team with regard to a few stakeholder requirements. What should the project manager do?

Options:

A.

Prioritize other items for the team and deal with the conflicting requirements later.


B.

Allow the project team to decide what is the most appropriate requirement to follow.


C.

Escalate to the project management office (PMO) and request a solution for the requirements.


D.

Negotiate a common agreement with the involved stakeholders regarding the requirements.


Expert Solution
Questions # 294:

A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The

project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.

What should the project manager do?

Options:

A.

Ask the experienced members to lead the junior members to facilitate skill transfer.


B.

Encourage team members to focus on delivering results with their specialized skills.


C.

Organize networking sessions to allow the team members to get to know one another.


D.

Ask the team to self-organize and escalate any issues to the project manager.


Expert Solution
Questions # 295:

A servant leader is about to start a confidential agile research project. A high risk has been identified related to a team member disclosing details of the project with external people.

What should the servant leader do to address this risk?

Options:

A.

Include this restriction as a ground rule and ensure all team members are familiar with it by reviewing the ground rules at the end of every

iteration.


B.

Forecast the cost of the risk to calculate the required contingency reserve that needs to be allocated if the risk materializes.


C.

Ask the functional manager to educate the team about this risk and ensure that disciplinary actions will be taken.


D.

Contact the human resources (HR) department to ensure that disciplinary actions will be taken if the employees disclose any confidential

information.


Expert Solution
Questions # 296:

A senior-level executive approached the project manager of a highly visible project that is currently in the execution phase. The executive indicated that they do not support the project

and will be actively trying to prevent its success by reailocating key team members to another critical project.

What should the project manager do?

Options:

A.

Request help from human resources to keep the key team members on the project.


B.

Work with the project sponsor to determine an appropriate response.


C.

Ask to meet privately with the senior-level executive to discuss the matter further.


D.

Discuss the incident with the key project team members.


Expert Solution
Questions # 297:

During the execution of a project, a company decides that everybody will need to take vacation time before the end of the year. This may cause a change in the project time line.

How should the project manager address the situation?

Options:

A.

Discuss the vacation plan and include scheduling changes in the change log database.


B.

Submit a formal request to senior management asking them not to proceed with this decision based on the impact it will have on the project.


C.

Agree with functional management and team members on a vacation schedule that would minimally impact the project schedule.


D.

Push out the project timeline according to the vacation plan in place based on the recent company policy.


Expert Solution
Questions # 298:

An agile project team is tasked with a new project After multiple discussions with me customer it appears that there is a lack of clarity on the requirements which resulted in delays in the architecture and design phase

What should the team do next?

Options:

A.

Start with the end user documentation review with the customer and gather feedback


B.

Start with design of the prototype review with the customer and gather feedback


C.

Start with the product prototype development, review with the customer, and gather feedback


D.

Start with the product architecture review with the customer and gather feedback


Expert Solution
Questions # 299:

A project is assigned to two different project teams to develop product features. One team uses a predictive approach and the other team uses an agile approach to complete the work. Senior management is concerned about the success of the project.

What should the project manager do?

Options:

A.

Advise the teams to follow the company’s existing project management approach.


B.

Allow the teams to continue using their approaches and gradually adapt to a hybrid model.


C.

Let a senior team member select the approach that is appropriate.


D.

Insist the teams both follow either a predictive or agile approach.


Expert Solution
Questions # 300:

During a project planning phase, the project manager realizes that project performance win be measured based on budget deviation and revenue, but without consideration for the overall project schedule What should the project manager do?

Options:

A.

Review and update the project schedule according to performance


B.

Review the schedule baseline and consider adopting a schedule performance indicator


C.

Develop a lime. cost, and scope tracking method exclusively for this project.


D.

Adopt a formal change management process for the project


Expert Solution
Viewing page 6 out of 12 pages
Viewing questions 251-300 out of questions