Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

Pass the PMI Project-Management-Professional PMP Questions and answers with CertsForce

Viewing page 6 out of 13 pages
Viewing questions 251-300 out of questions
Questions # 251:

A project manager is working on a software development project. The project manager and the project team identified the project risks. As the

project progressed, one of the risks materialized, and the project manager referred to the risk management plan to determine how to manage the risk. Once the risk management strategy was chosen and implemented, the risk was closed.

At what point did the project manager move the risk from the risk register to the issue log?

Options:

A.

Risk monitored


B.

Risk occurred


C.

Risk managed


D.

Risk identified


Expert Solution
Questions # 252:

A team realizes that there is no access to data that the project depends on to complete the current iteration. This dependency was known; however, the team is unsure of the available options to remove this obstacle.

What should the project manager do next?

Options:

A.

Guide the team to determine alternatives.


B.

Move the dependent task to the next iteration.


C.

Escalate the issue to the company's IT manager.


D.

Escalate the issue to the project sponsor.


Expert Solution
Questions # 253:

The current incremental revenue expected by a project deliverable is not fulfilling the business case requirement The deliverable was already closed and handed over to the operations team

Which two actions should the project manager take? (Choose two)

Options:

A.

Review the issue with project sponsor and submit a change request


B.

Report the issue to the product manager and business segments


C.

Analyze the business benefits criteria and assumptions


D.

Discuss the issue with the operations team to assess expense overruns


E.

Schedule a project review meeting to analyze the root cause


Expert Solution
Questions # 254:

A project manager is reviewing the team's Kanban board for an iteration with 16 tasks in progress. All the tasks are equally sized with an estimate of 8 man-hours of effort needed to complete each task. The team is made up of five cross-functional members. The normal working calendar is 8 hours per day; however, two of the team members will only work at 50% capacity. The project manager has a maximum of one week to deliver these tasks in progress due to government regulations.

Will the project manager meet this objective?

Options:

A.

Yes, it will take 4 working days to complete these tasks based on the estimate.


B.

No, it will take 6 days to complete all these tasks based on the estimate.


C.

No, it will take 7 days to complete all these tasks based on the estimate.


D.

Yes, it will take 5 working days to complete these tasks based on the estimate.


Expert Solution
Questions # 255:

A project team needs to create artifacts for an upcoming steering committee.

What should the project manager do first?

Options:

A.

Use templates from an existing project.


B.

Ask the project management office (PMO) for guidance.


C.

Surveying peers to understand what templates they have used.


D.

Lead the project team in finding the best templates.


Expert Solution
Questions # 256:

A new agile project is starting. The project manager is asked to confirm the scope to address the concerns of one of the stakeholders.

What should the project manager use to explain the project scope?

Options:

A.

Product roadmap


B.

User stories


C.

Business requirements document


D.

Product backlog


Expert Solution
Questions # 257:

A flagship project is sponsored by the CEO and has a critical go-live date. The project's product requires a regulatory review and approval before it can go live. The CEO instructed to allow only 2 weeks for regulatory approval in the schedule; however, the director for the regulatory liaison indicated 6 weeks was a more realistic timeline.

What should the project manager do?

Options:

A.

Proceed with the direction given by the director for the regulatory liaison, as they are the subject matter expert (SME).


B.

Follow the CEO's directive, as they are the highest authority in the company and are the ultimate decision maker.


C.

Meet with the CEO and the director to discuss and register it as a major risk if agreement cannot be made.


D.

Schedule final testing activities in parallel with the regulatory approval activities to compensate for lost time.


Expert Solution
Questions # 258:

A project manager acquired information from the market that would reduce the business value being delivered by an ongoing protect Based on that information, the project manager believes the project should be stopped

How should the project manager handle the situation?

Options:

A.

Remove the items no longer applicable from the backlog and present the backlog to the project team


B.

Continue working on the defined scope and review the risk matrix


C.

Have a discussion with the project sponsor and cancel the project


D.

Have a discussion with the sponsor and recommend the project business value be reassessed


Expert Solution
Questions # 259:

A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.

What should the project manager do next ?

Options:

A.

Use the team's connections with international colleagues to get early warnings on future changes.


B.

Keep the focus on the priority items while the change goes through the change control process.


C.

Reject the change request since it may negatively impact the project's performance.


D.

Implement the change request as soon as possible to avoid accumulating new scope.


Expert Solution
Questions # 260:

At a project meeting, a business analyst requires input from a marketing consultant to continue working on a task. The business analyst has tried

to contact the consultant but has been told that the consultant does not have the time to discuss the project.

What should the project manager do to move the project forward?

Options:

A.

Escalate the issues about the consultant to the functional manager so the consultant dedicates the necessary time to the project.


B.

Include a new project risk into the risk register and allocate the consultant as the risk owner as it is their responsibility to provide input.


C.

Discuss the request with the consultant and set up time with the business analyst and consultant to discuss the project requirements.


D.

Urge the business analyst to continue contacting the consultant to discuss the project since this is the responsibility of the business analyst.


Expert Solution
Questions # 261:

An organization is struggling to start an important project. The project manager has identified that the scope definition is the main item preventing

the project from starting. Although most of the scope items are defined and agreed upon among the stakeholders, there are a few items that are hard to grasp and very complex to define at this stage.

What should the project manager do?

Options:

A.

Recommend splitting the project into two smaller projects in order to work exclusively in an agile environment without interference from a predictive approach.


B.

Propose that the well-defined scope items be delivered using a predictive approach and use an agile approach to deal with the complexitems.


C.

Maintain stakeholder momentum in working on the scope definition until a full detailed scope is achieved prior to starting the project.


D.

Update the risk register and escalate the issue to the project management office (PMO), requesting more resources be added to help definethe project scope.


Expert Solution
Questions # 262:

A project manager is assigned to develop a wire bending machine midway through the design phase. The project manager discovered that the team did not have any test cases or acceptance criteria tor the equipment. The project manager started communication with the team to move the project forward

What should the project manager do first at this pomp

Options:

A.

Meet with the quality planning manager to identify the reason why the quality plan was not created yet


B.

Meet with the hardware design engineers to identify the minimum performance required to establish a market for the machine


C.

Meet with the sales and marketing teams to identify the requirements that were collected during the interview sessions with potential customers


D.

Meet with the key stakeholders to identify the proper product concept for the development team


Expert Solution
Questions # 263:

A hybrid project team is working on an upgraded version of software for their

product owner. The team is also responsible for supporting the existing product and

customers. For the last three sprints, the team had to stop their project work and focus on

major support items for the product owner. The testers are struggling to cope with the

constant changes to the plan, which has resulted in a number of emotional outbursts.

How should the project manager proceed?

Options:

A.

Request a replacement for those team members who are unhappy with this way ofworking.


B.

Schedule a session with the product owner to explain that no support items can betaken into the sprints going forward.


C.

Ask human resources (HR) to send the team members to a change managementworkshop.


D.

Schedule a session with the team to discuss the issues and work with them to define aplan to manage the sprints going forward.


Expert Solution
Questions # 264:

A project team has been together for a long time and has been led by three different

project managers. Lately, the performance of one of the team members has been declining

and has affected the project delivery.

What should the current project manager do to ensure that team performance is improved and

sustained?

Options:

A.

Liaise with the functional managers to replace the team member.


B.

Engage with the team member and draw up a development plan.


C.

Organize quarterly team-building events.


D.

Request that a new team member be added to the team


Expert Solution
Questions # 265:

During the setup of an agile project, the product owner expressed clear interest in having features released during product development over having the product completed in one year. What should the project manager do?

Options:

A.

Design a set of metrics including velocity, which is a good measure of value delivered.


B.

Facilitate sprint planning sessions with a focus on defining the minimum viable product (MVP)


C.

Promote a productive environment where everybody can work without interruptions from the rest of the team members


D.

Create a reward system recognizing group contributions to get people motivated and improve performance


Expert Solution
Questions # 266:

A project manager who works for a company involved in several industries is asked

to lead a software development project for a government agency. The company attempted to

execute similar projects for other industries before but was unsuccessful.

What should the project manager do to ensure project success?

Options:

A.

Document this information in the risk management plan.


B.

Develop a contingency plan to prepare for possible risks.


C.

Continue executing the project using expert judgment.


D.

Review the lessons learned registers from the previous projects.


Expert Solution
Questions # 267:

A project manager realizes that the team members are new to the hybrid approach and do not value standup meetings. Team members often arrive late. Digress into solutioning. or skip the meetings altogether.

How should the project manager improve this situation with the project team?

Options:

A.

Engage the project team In implementing and Improving key aspects of the standup meetings.


B.

Ask the product owner to remove team members who do not comply with standup meeting rules.


C.

Send a daily retrospective report to all team members instead of holding standup meetings.


D.

Include a daily brainstorming session In the standup meetings to resolve pending Issues.


Expert Solution
Questions # 268:

A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.

What should the project manager do to address the concem9

Options:

A.

Provide team-building activities so that the team can learn how to overcome disruptive behavior


B.

Inform the disruptive team member's functional manager that the disruptive behavior should be stopped immediately


C.

Request a meeting with the disruptive team member and help to resolve the issue


D.

Encourage self-governance and ask the concerned team member to speak to the disruptive team member directly


Expert Solution
Questions # 269:

A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed

To what type of communication is the team member referring?

Options:

A.

Mass communication


B.

Push communication


C.

Pull communication


D.

Interactive communication


Expert Solution
Questions # 270:

A project team is facing challenges understanding how to deliver a project's scope.

A senior subject matter expert (SME) from the organization's global office is in town for 1 week.

What should the project manager do to benefit from the SME's presence?

Options:

A.

Ask the SME to review the scope for alignment with the project charter.


B.

Organize a mentoring session with the team and the SME.


C.

Meet with the SME to discuss the current challenges the team is facing.


D.

Review the project scope statement with the SME.


Expert Solution
Questions # 271:

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule

What should the project manager do?

Options:

A.

Advise the project management office (PMO) that there is a resource gap for sharing project artifacts effectively


B.

Escalate the issue to the steering committee and ask them to deal with the stakeholders' lack of training


C.

Make sure all stakeholders have access to the system and know where to find project artifacts


D.

Send the project schedule via email to the stakeholders who need that information


Expert Solution
Questions # 272:

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?

Options:

A.

Held a touchpoint with marketing before the demo to discuss any impediments


B.

Scheduled a demo presentation of the product during the first reason


C.

Asked the marketing team to start working on the product immediately


D.

Confirmed marketing requirements and constraints when adding to the backlog


Expert Solution
Questions # 273:

The project manager realizes that the product owner has a lot of potential but is lacking communication skills. How should the project manager help the product owner to develop these skills while executing the project?

Options:

A.

Ensure there are opportunities for the product owner to present project reviews to the stakeholders.


B.

Suggest that the product owner attend a training session about assertive communication.


C.

Suggest that the product owner shadow colleagues who are good presenters.


D.

Recommend a specialized article about delivering effective presentations to the product owner.


Expert Solution
Questions # 274:

An agile project manager has learn members from different continents on the project team. During the dairy scrum meetings the project manager notices that there are gaps in understanding about the project goals and objectives

What should the project manager do?

Options:

A.

Schedule team-building activities to encourage collaboration among the team


B.

Coach the team members to resolve the gaps in understanding


C.

Conduct a kick-off meeting and communicate the goals and objectives of the project


D.

Continue the meetings and communicate the goals and objectives to resolve the gaps


Expert Solution
Questions # 275:

A new project manager is managing a hybrid project. The project manager wants to be

a servant leader to support the team by removing impediments but is not receiving feedback

from the team about the issues and risks they are facing.

What should the project manager do?

Options:

A.

Implement daily standups where the team can share their impediments, risks, andissues.


B.

Review the communications management plan and implement changes.


C.

Schedule weekly risk review meetings with the team to review project risks andconcerns.


D.

Distribute a copy of the communications management plan to the scrum master.


Expert Solution
Questions # 276:

A newly appointed product owner is working with a project team that is using agile

for the first time. The product owner is constantly disrupting various team members throughout

the day to discuss progress. This has resulted in the team feeling micromanaged and

frustrated because of the constant disruptions.

How should the project manager proceed?

Options:

A.

Invite the product owner to attend daily standup meetings so they can assessprogress.


B.

Set up a feedback session with the product owner once a week so they can assessprogress.


C.

Instruct the team to refer the product owner to the project manager for information.


D.

Invite the product owner's functional manager to a feedback session to escalate theissue.


Expert Solution
Questions # 277:

A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.

What should the project manager do?

Options:

A.

Suggest an agile approach to refine these requirements and prioritize them according to the project objectives


B.

Validate the prioritization of all requirements with the sponsor and share the results with the stakeholders


C.

Review the project governance to validate the policies procedures and guidelines used to prioritize the project


D.

Ask the stakeholders to refine these requirements at a level of detail that becomes more stable and measurable


Expert Solution
Questions # 278:

A developer who has almost completed a required product feature for a prototype

leaves the company in the middle of an iteration. What should the project manager do?

Options:

A.

Review the backlog to reschedule the deliverable for a later iteration.


B.

Engage with stakeholders directly to review the iteration process.


C.

Determine whether other cross-functional team members are able to take over thework.


D.

Go to management and ask to hire a new external developer.


Expert Solution
Questions # 279:

A project manager is assigned to a new water treatment plant project that has been

delayed for many years. It is revealed in the project charter that the sponsors of this project

are from three different business units. This is the first time the sponsors have ever

implemented such a project.

What should the project manager do?

Options:

A.

Establish mentoring and coaching sessions.


B.

Review the knowledge repository for similar projects.


C.

Schedule the project kick-off meeting immediately.


D.

Meet with the project sponsors to align expectations


Expert Solution
Questions # 280:

A project team Is working on a relative-weighting approach to assess product features. The product features will be prioritized to highlight the benefits and bring value to the customer.

What should the project manager ask the team to do?

Options:

A.

Perform collaborative work that is coordinated by the project manager.


B.

Rely on the expert judgment of the product owner.


C.

Use a market-based strategy.


D.

Engage the project sponsor.


Expert Solution
Questions # 281:

A project manager is leading an integration project for a retail company. The project

demands a lot of time from the stakeholders to make important business decisions. The

project is critical and must be completed on time and within budget.

What should the project manager do to ensure that key stakeholders are available for this

project?

Options:

A.

Schedule meetings with all of the stakeholders to make business decisions whenneeded.


B.

Share the project schedule, milestones, and meeting agendas with the stakeholdersahead of time.


C.

Work with the available stakeholders to make business decisions and keep allunavailable stakeholders informed.


D.

Add time reserve in the project schedule to allow extra time for the stakeholders tomake decisions.


Expert Solution
Questions # 282:

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?

Options:

A.

Encourage and motivate the team with project incentives


B.

Subdivide the team to handle different aspects of the project


C.

Support the team to find and execute the minimum viable product (MVP)


D.

Organize project execution to satisfy the project sponsor s request


Expert Solution
Questions # 283:

A project leader is assigned to a new project and is asked to assemble an effective

five-member agile team. If the project leader has no restrictions, which team should they

choose?

Options:

A.

A team whose members work independently and are the best subject matter experts(SMES)


B.

A team whose members have more general aptitudes but like to work individually


C.

A team whose members have different skill sets and are spread out geographically


D.

A team whose members have more general aptitudes and can collaborate on different tasks


Expert Solution
Questions # 284:

A project manager is tasked with large deliverables that require work by several top developers over the next few weeks Because of the size and complexity of the deliverables the work cannot be assigned to a single person

What should the project manager do first?

Options:

A.

Request additional developers to join the project team through the change cannot process


B.

Break down the deliverable by using the work breakdown structure (WBS) process to make it more manageable for task assignment


C.

Assign the entire deliverable to the first available developer to lead and have them assign the work to the remaining developers


D.

Include the situation as a risk in the risk register identify risk impacts and possible mitigations, and monitor closely


Expert Solution
Questions # 285:

During the early phases of a project, mitigation actions were not executed in a

timely manner; therefore, the project schedule was impacted. Several project stakeholders are

now frustrated with the delays.

What should the project manager have done to manage the issue?

Options:

A.

Identified and reported the issue


B.

Monitored and controlled the issue


C.

Identified the appropriate response and had it implemented


D.

Communicated any identified action to impacted stakeholders


Expert Solution
Questions # 286:

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?

Options:

A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal andexternal resource requirements.


B.

Commit each team member's time and deliverables and aim for overall projectcompletion.


C.

Continue the project implementation without the site engineers to ensure the scheduleis maintained.


D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.


Expert Solution
Questions # 287:

As a project is reaching completion, the project sponsor tells the project manager to

immediately close the project and to move on to another project. Which critical task should the

project manager complete before closing the project?

Options:

A.

Ensure that the whole team is appropriately recognized and organize a project farewellparty to celebrate the project success and closure.


B.

Update and close both the risk register and issue log with the latest updates, and savethem in the organization's project management information system (PMIS).


C.

Archive all the project documents following the organization's accepted practices sothe documents can be used in other future projects.


D.

Meet with the project sponsor and advise that the new project might be difficult toundertake because the current project is not yet complete.


Expert Solution
Questions # 288:

During the execution of a construction project, the project sponsor asks to make

changes to the floor plan by adding a minimal storage room. The sponsor insists on making

this last-minute change, but they would like to avoid delays to the project.

Which document should the project manager refer to first?

Options:

A.

Change management plan


B.

Schedule management plan


C.

Scope management plan


D.

Cost management plan


Expert Solution
Questions # 289:

A project manager receives a serious complaint from a functional manager about a

team member. What should the project manager do?

Options:

A.

Replace the team member immediately to maintain a good relationship with thefunctional manager.


B.

Discuss the issue with the functional manager to understand the reason for thecomplaint.


C.

Support the team member and provide documentation to the functional managerproving their performance.


D.

Protect the team member and ask the project sponsor to minimize any externalinterruptions.


Expert Solution
Questions # 290:

One of the team members is consistently absent in team meetings, but always completes their assigned tasks on time. Other team members think this member should attend the meetings.

What should the project manager do?

Options:

A.

Assign this member to facilitate the next meeting to ensure project team collaboration.


B.

Allow each team member to submit their required tasks on time and reduce the number of scheduled meetings.


C.

Review and update the project ground rules to make meeting attendance mandatory.


D.

Understand the reason for the team member's absence and encourage them to attend future meetings.


Expert Solution
Questions # 291:

A project with multiple teams recently transitioned from a predictive approach to agile

as requested by the product owner. Midway through implementation, a team member noticed

there was no technical capability to support the current business requirement; therefore, the

project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?

Options:

A.

Assessed the technical and organizational readiness for the project and identified risksat the beginning of the first iteration


B.

Requested the product owner's approval to add an external expert to define theacceptance criteria


C.

Defined a clear acceptance criteria at the initiation phase and continued with theproject


D.

Increased the communications between the team member and the product owner


Expert Solution
Questions # 292:

During a network upgrade for a company, the client informs the project manager that a government representative notified the client about a separate project that will affect the network upgrade. Any change in the upgrade will impact the project's cost and schedule.

What should the project manager do first?

Options:

A.

Perform an impact analysis with subject matter experts (SMEs).


B.

Inform the government representative about the impact of the separate project.


C.

Implement a change request to increase the budget and schedule.


D.

Consult and update the risk register with the project stakeholders.


Expert Solution
Questions # 293:

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?

Options:

A.

Workstream leader and project sponsor


B.

Workstream leader alone


C.

Workstream leader and functional manager


D.

Workstream leader and project management office (PMO)


Expert Solution
Questions # 294:

During a documentation audit of an international company it was identified that the last version of the protect schedule was from one month ago even though the project manager kr. it was recently updated How should the project manager have handled documentation for the project?

Options:

A.

Reviewed the risk register to identify a response plan for the audit


B.

Assigned a project team member to ensure all project documentation was updated


C.

Updated the project management plan regularly and had it securely shared with all stakeholders


D.

Kept documentation in the project management information system (PMIS) and shared it with appropriate stakeholders


Expert Solution
Questions # 295:

An agile project manager has just been given a sizeable software development project to implement. Early in the initiation stage, the project sponsor requests an indication of time lines for delivery of the initial release.

What tools should the agile project manager use to do these estimates?

Options:

A.

Product backlog, budget, resource management plan


B.

Budget, minimum viable product (MVP), retrospective notes


C.

Resource management plan, retrospective notes, backlog grooming


D.

Backlog grooming, product backlog, minimum viable product (MVP)


Expert Solution
Questions # 296:

A project manager is working on a large project in another country and realizes that

only a few people from the project team are working on all of the releases. What should the

project manager do to prevent this in the future?

Options:

A.

Document the risk register in the project charter.


B.

Speak to the customer and add the issue to the issue log.


C.

Review user roles and update the team charter.


D.

Involve the product owner to rewrite the user stories.


Expert Solution
Questions # 297:

A project manager is establishing a project management office (PMO) for a

company-wide program to implement a software based on artificial intelligence (AI). As part of the PMO tasks, some stakeholders need help understanding how to deal with difficult situations.

Which activity should the project manager use to help train the stakeholders?

Options:

A.

Contract negotiation


B.

Team assessment


C.

Mentoring and coaching


D.

On-the-job training


Expert Solution
Questions # 298:

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?

Options:

A.

Motivate the team and deploy the necessary resources.


B.

Find a way to maintain the project schedule.


C.

Impose authority on the project.


D.

Request additional resources from the sponsor and motivate the team.


Expert Solution
Questions # 299:

A new building project is in the middle of its life cycle. The municipality informs the project manager that due to new regulations, the parking lot around the project has to accommodate twice the number of cars than was initially planned.

What should the project manager do next?

Options:

A.

Request the project sponsor to fund this change as it is a new regulation, then order the materials in order to start working.


B.

Assess the impact of the required change and consult with the executive sponsors to determine the best course of action.


C.

Ask the designers to start designing a solution for this new requirement while the project is running and determine the funding for this change.


D.

Have the company's lawyers write to the municipality and reject the change as it was not part of the scope approved by the municipality.


Expert Solution
Questions # 300:

A project manager is leading a software development project. Recently, team members have complained that during the last few dally standup meetings, a key stakeholder frequently interrupts, requests explanations, and proposes unplanned changes. This issue is frustrating the project team and slowing down me work.

What should the project manager do?

Options:

A.

Instruct the team to work as planned and Ignore the stakeholder's requests.


B.

Escalate the situation to upper management.


C.

Add more team members to make up for any project delays.


D.

Address the issue with the stakeholder and explain the situation.


Expert Solution
Viewing page 6 out of 13 pages
Viewing questions 251-300 out of questions