PMI Project Management Professional (2025 Version) PMP Question # 282 Topic 29 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 282 Topic 29 Discussion

PMP Exam Topic 29 Question 282 Discussion:
Question #: 282
Topic #: 29

A project manager is developing the stakeholder register and is having trouble understanding the motivation of some of the stakeholders. What should the project manager

do to get this information?


A.

Organize a one-on-one conversation with each stakeholder.


B.

Request stakeholders articulate their motivations at the kick-off meeting.


C.

Email project objectives to all stakeholders and ask for endorsement.


D.

Identify each stakeholder's motivations from the business case.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.