Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 282 Topic 29 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 282 Topic 29 Discussion

PMP Exam Topic 29 Question 282 Discussion:
Question #: 282
Topic #: 29

A project sponsor wants to develop software that would have 30 features and would be used in 10 different countries. The team feels overwhelmed with the amount of work to be done. What should the project manager do?


A.

Encourage and motivate the team with project incentives


B.

Subdivide the team to handle different aspects of the project


C.

Support the team to find and execute the minimum viable product (MVP)


D.

Organize project execution to satisfy the project sponsor s request


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.