Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 268 Topic 27 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 268 Topic 27 Discussion

PMP Exam Topic 27 Question 268 Discussion:
Question #: 268
Topic #: 27

A concerned project team member complains to the project manager that another team member is being disruptive and argumentative during team meetings. The project manager received some information that the team member recently overcame a difficult personal situation.

What should the project manager do to address the concem9


A.

Provide team-building activities so that the team can learn how to overcome disruptive behavior


B.

Inform the disruptive team member's functional manager that the disruptive behavior should be stopped immediately


C.

Request a meeting with the disruptive team member and help to resolve the issue


D.

Encourage self-governance and ask the concerned team member to speak to the disruptive team member directly


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.