The project manager is reviewing a project's progress and notices that one of the risks has become an issue. What should the project manager do to address the situation?


A.

Schedule a high-priority meeting with the project stakeholders to discuss the issue.


B.

Initiate a change request to obtain additional funds from the management reserve.


C.

Meet with the project team and customer to brainstorm about potential solutions.


D.

Collaborate with the relevant stakeholders on implementing the risk response plan.