PMI Project Management Professional (2025 Version) PMP Question # 269 Topic 27 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 269 Topic 27 Discussion

PMP Exam Topic 27 Question 269 Discussion:
Question #: 269
Topic #: 27

A project using a hybrid approach to migrate from a current system to a new and

enhanced system is underway. The plan is to migrate the system in stages. However, the

operations team is complaining that they are not ready to start supporting the new system.

How should the project manager effectively approach this situation?


A.

Create a lessons learned register to include operations team training for future projects.


B.

Include knowledge transfer sessions between the project and operations teams at every stage.


C.

Change the project management plan to add a final stage for product handoff to the operations team.


D.

Prepare detailed documentation to be shared with the operations team during project closure.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.