Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 269 Topic 27 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 269 Topic 27 Discussion

PMP Exam Topic 27 Question 269 Discussion:
Question #: 269
Topic #: 27

A project interfaces with other projects that are in the same portfolio but are being developed in international locations. One of the international projects has suggested a tactical change that needs to be implemented in this project.

What should the project manager do next ?


A.

Use the team's connections with international colleagues to get early warnings on future changes.


B.

Keep the focus on the priority items while the change goes through the change control process.


C.

Reject the change request since it may negatively impact the project's performance.


D.

Implement the change request as soon as possible to avoid accumulating new scope.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.