PMP Exam Topic 27 Question 269 Discussion:
Question #: 269
Topic #: 27

A project manager has heard about the large volume of emails the team receives each day which prevents them from doing project work. One team member has stated that they would like to be able to access project-related information when needed

To what type of communication is the team member referring?


A.

Mass communication


B.

Push communication


C.

Pull communication


D.

Interactive communication