PMI Project Management Professional (2025 Version) PMP Question # 270 Topic 28 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 270 Topic 28 Discussion

PMP Exam Topic 28 Question 270 Discussion:
Question #: 270
Topic #: 28

During the execution phase of a project a new project manager is assigned to replace the previous project manager As the project manager starts managing the project, they discover that team performance is significantly decreasing, which is impacting the project's key performance indicators (KPIs). This team has delivered good performance on similar projects in the past

What should the project manager do next to improve this situation?


A.

Call for a team meeting to identify the root cause for the declining performance


B.

Estimate the baseline impacts and submit a change request.


C.

Implement compression techniques to bring the project back on track.


D.

Review the resource management plan and organizational assets


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.