Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 272 Topic 28 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 272 Topic 28 Discussion

PMP Exam Topic 28 Question 272 Discussion:
Question #: 272
Topic #: 28

In an iteration-based marketing project, a product is scheduled to be launched at the sixth iteration In the third iteration demo the marketing team expressed that they need five iterations to launch the product and they have not started yet

What should the project team have done to avoid this issue?


A.

Held a touchpoint with marketing before the demo to discuss any impediments


B.

Scheduled a demo presentation of the product during the first reason


C.

Asked the marketing team to start working on the product immediately


D.

Confirmed marketing requirements and constraints when adding to the backlog


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.