Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 271 Topic 28 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 271 Topic 28 Discussion

PMP Exam Topic 28 Question 271 Discussion:
Question #: 271
Topic #: 28

A project manager is managing a hybrid project. There is software in place to access the repository of project artifacts However a few stakeholders are reporting that they are unable to find the latest project schedule

What should the project manager do?


A.

Advise the project management office (PMO) that there is a resource gap for sharing project artifacts effectively


B.

Escalate the issue to the steering committee and ask them to deal with the stakeholders' lack of training


C.

Make sure all stakeholders have access to the system and know where to find project artifacts


D.

Send the project schedule via email to the stakeholders who need that information


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.