PMI Project Management Professional (2025 Version) PMP Question # 271 Topic 28 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 271 Topic 28 Discussion

PMP Exam Topic 28 Question 271 Discussion:
Question #: 271
Topic #: 28

A team member has indicated their user story will not be finished until the end of the iteration as their functional manager has requested they assist in resolving a high-priority production issue. What should the project manager do?


A.

Discuss with the product owner that the user story will not be completed this iteration.


B.

Meet with the team member's functional manager to try to remove the impediment.


C.

Tell the project team member not to work on the production issue and to inform their manager.


D.

Escalate the issue to the project sponsor to resolve and adjust the project burndown chart.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.