Spring Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 274 Topic 28 Discussion

PMI Project Management Professional (PMBOK 7th Version) PMP Question # 274 Topic 28 Discussion

PMP Exam Topic 28 Question 274 Discussion:
Question #: 274
Topic #: 28

A project manager has been assigned to a new project that is similar to a project that was closed last year. There is no schedule baseline, but the project manager received the activity list and wants to prepare a reasonable schedule.

What should the project manager do?


A.

Adopt the same timeframe as the closed project for the current project.


B.

inform the sponsor that the activity list is not adequate for creating a schedule baseline.


C.

Create a draft schedule based on the activity list and the historical data from the closed project.


D.

Evaluate each activity duration and build a new project schedule.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.