PMI Project Management Professional (2025 Version) PMP Question # 275 Topic 28 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 275 Topic 28 Discussion

PMP Exam Topic 28 Question 275 Discussion:
Question #: 275
Topic #: 28

A project is on its second iteration out of six. The team realizes that a key deliverable will depend on the acquisition of a new device.

What should the project manager do?


A.

Register a risk and escalate it to the project sponsor.


B.

Include the responsibility for acquisition with the core team.


C.

Detail the reason for the deliverable delay in the status report.


D.

Invite the stakeholders to discuss prioritization of a new deliverable.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.