Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 275 Topic 28 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 275 Topic 28 Discussion

PMP Exam Topic 28 Question 275 Discussion:
Question #: 275
Topic #: 28

A new project manager is managing a hybrid project. The project manager wants to be

a servant leader to support the team by removing impediments but is not receiving feedback

from the team about the issues and risks they are facing.

What should the project manager do?


A.

Implement daily standups where the team can share their impediments, risks, andissues.


B.

Review the communications management plan and implement changes.


C.

Schedule weekly risk review meetings with the team to review project risks andconcerns.


D.

Distribute a copy of the communications management plan to the scrum master.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.