Question #: 295
Topic #: 30

A project team member identified a procurement risk and sent an email to the project sponsor highlighting the risk.

The sponsor forwarded the email to the project manager asking for further details. After speaking with the sponsor, the project manager decided to take preventive action.

Which document should the project manager review with their team?


A.

Risk management plan


B.

Quality management plan


C.

Communications management plan


D.

Procurement management plan