PMI Project Management Professional (2025 Version) PMP Question # 296 Topic 30 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 296 Topic 30 Discussion

PMP Exam Topic 30 Question 296 Discussion:
Question #: 296
Topic #: 30

While working with the project team on planning project resources, the project manager discovers that a critical resource will be assigned at the same time to another project in the organization. The project team explains to the project manager that this resource cannot be replaced by another resource.

What should the project manager do first?


A.

Contact the human resources (HR) department to find new resources to replace this critical resource.


B.

Meet with the project lead of the other project to evaluate how to best allocate the critical resource in both projects.


C.

Ask the project team to reschedule the project tasks that will demand the use of this critical resource.


D.

Discuss the resource management plan with the project team for effective utilization of critical resources.