PMP Exam Topic 30 Question 298 Discussion:
Question #: 298
Topic #: 30

A company is interested in reducing production costs in one of its production lines. When the project charter was about to be approved, one of the key stakeholders questioned the project's value and caused a delay in the approval.

What should the project manager have done to avoid this setback?


A.

Assessed feasibility and impacts


B.

Developed benchmarking


C.

Analyzed stakeholders


D.

Detailed the project charter


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.