PMP Exam Topic 30 Question 298 Discussion:
Question #: 298
Topic #: 30

After difficult negotiations, a customer committed to pay the cost for changes to the

project scope. The team seems unhappy as the project completion time will take longer than

previously scheduled.

How should the project manager support the outcome of the new agreement?


A.

Motivate the team and deploy the necessary resources.


B.

Find a way to maintain the project schedule.


C.

Impose authority on the project.


D.

Request additional resources from the sponsor and motivate the team.