PMI Project Management Professional (2025 Version) PMP Question # 258 Topic 26 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 258 Topic 26 Discussion

PMP Exam Topic 26 Question 258 Discussion:
Question #: 258
Topic #: 26

An organization uses a predictive approach but is open to using some agile practices. The project manager was asked to recommend an agile practice to provide business value throughout the project.

What should the project manager recommend?


A.

Time-boxed iterations to allow the testing team to thoroughly test the product increments


B.

Incremental delivery and frequent backlog refinement based on user feedback


C.

Iterative development and collection of frequent feedback from project team members


D.

Frequent retrospectives to ensure that lessons learned and improvement actions are implemented