PMI Project Management Professional (2025 Version) PMP Question # 287 Topic 29 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 287 Topic 29 Discussion

PMP Exam Topic 29 Question 287 Discussion:
Question #: 287
Topic #: 29

A project scope statement has been approved, and the project manager and core team have been assigned to the project. Suddenly, the project

manager takes a temporary leave of absence due to a medical emergency. While the project manager is on leave, the team develops the project

schedule. When the project manager returns, a detailed schedule is almost complete.

What should the project manager do?


A.

Ensure that the schedule is aligned with the vision and objectives.


B.

Escalate the compliance issue to the project management office (PMO).


C.

Congratulate the team and move on to the execution phase.


D.

Develop a new detailed schedule with the team and project sponsor.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.