Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 287 Topic 29 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 287 Topic 29 Discussion

PMP Exam Topic 29 Question 287 Discussion:
Question #: 287
Topic #: 29

As a project is reaching completion, the project sponsor tells the project manager to

immediately close the project and to move on to another project. Which critical task should the

project manager complete before closing the project?


A.

Ensure that the whole team is appropriately recognized and organize a project farewellparty to celebrate the project success and closure.


B.

Update and close both the risk register and issue log with the latest updates, and savethem in the organization's project management information system (PMIS).


C.

Archive all the project documents following the organization's accepted practices sothe documents can be used in other future projects.


D.

Meet with the project sponsor and advise that the new project might be difficult toundertake because the current project is not yet complete.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.