Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 286 Topic 29 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 286 Topic 29 Discussion

PMP Exam Topic 29 Question 286 Discussion:
Question #: 286
Topic #: 29

A business improvement opportunity to reduce energy usage has been identified.

The project manager has assembled a team that includes site engineers to deliver this project.

However, due to production imperatives, the site engineers may not be fully focused on the

project.

How should the project manager manage the team?


A.

Develop an approved responsibility assignment matrix (RAM) to confirm internal andexternal resource requirements.


B.

Commit each team member's time and deliverables and aim for overall projectcompletion.


C.

Continue the project implementation without the site engineers to ensure the scheduleis maintained.


D.

Contract external resources to fulfill the role of the site engineers who cannot support the project.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.