Question #: 289
Topic #: 29

A project manager receives a serious complaint from a functional manager about a

team member. What should the project manager do?


A.

Replace the team member immediately to maintain a good relationship with thefunctional manager.


B.

Discuss the issue with the functional manager to understand the reason for thecomplaint.


C.

Support the team member and provide documentation to the functional managerproving their performance.


D.

Protect the team member and ask the project sponsor to minimize any externalinterruptions.