Big Halloween Sale Limited Time 70% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: simple70

PMI Project Management Professional (2025 Version) PMP Question # 291 Topic 30 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 291 Topic 30 Discussion

PMP Exam Topic 30 Question 291 Discussion:
Question #: 291
Topic #: 30

A project with multiple teams recently transitioned from a predictive approach to agile

as requested by the product owner. Midway through implementation, a team member noticed

there was no technical capability to support the current business requirement; therefore, the

project will need to be reworked and the issue needs to be communicated to all stakeholders.

What should the agile project lead have done to avoid this situation?


A.

Assessed the technical and organizational readiness for the project and identified risksat the beginning of the first iteration


B.

Requested the product owner's approval to add an external expert to define theacceptance criteria


C.

Defined a clear acceptance criteria at the initiation phase and continued with theproject


D.

Increased the communications between the team member and the product owner


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.