PMI Project Management Professional (2025 Version) PMP Question # 291 Topic 30 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 291 Topic 30 Discussion

PMP Exam Topic 30 Question 291 Discussion:
Question #: 291
Topic #: 30

A project manager is leading a project in which the product requirements have not been fully met due to several uncertainties about customer acceptance. What should the project manager do?


A.

Gather a reduced number of approved requirements and add some extra features to fulfill the product specifications.


B.

Ask team members to research and collect data about the best features offered by similar products in the market.


C.

Stop all project activities until all requirements are set up front by the project sponsor and the key stakeholders.


D.

Gather enough requirements to produce a minimum viable product (MVP) with which to evaluate customer acceptance.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.