PMI Project Management Professional (2025 Version) PMP Question # 292 Topic 30 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 292 Topic 30 Discussion

PMP Exam Topic 30 Question 292 Discussion:
Question #: 292
Topic #: 30

Construction work is preventing the project team members from entering the building where their offices are located.

What should the project manager do next?


A.

Inform the authorities so that they are aware of the situation and can take appropriate action.


B.

Continue business as usual since the construction work is not related to the project.


C.

Select the next action to be taken according to the risk management plan.


D.

Communicate with the stakeholders about the construction and ask for direction.


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.