Pre-Winter Sale Limited Time 65% Discount Offer - Ends in 0d 00h 00m 00s - Coupon code: pass65

PMI Project Management Professional (2025 Version) PMP Question # 293 Topic 30 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 293 Topic 30 Discussion

PMP Exam Topic 30 Question 293 Discussion:
Question #: 293
Topic #: 30

A project manager is working on a project with multiple workstreams. One of the

workstreams missed its deadline multiple times.

Who should the project manager speak to about this situation to ensure it does not happen

again?


A.

Workstream leader and project sponsor


B.

Workstream leader alone


C.

Workstream leader and functional manager


D.

Workstream leader and project management office (PMO)


Get Premium PMP Questions

Contribute your Thoughts:


Chosen Answer:
This is a voting comment (?). It is better to Upvote an existing comment if you don't have anything to add.