Question #: 288
Topic #: 29

During the execution of a construction project, the project sponsor asks to make

changes to the floor plan by adding a minimal storage room. The sponsor insists on making

this last-minute change, but they would like to avoid delays to the project.

Which document should the project manager refer to first?


A.

Change management plan


B.

Schedule management plan


C.

Scope management plan


D.

Cost management plan