PMI Project Management Professional (2025 Version) PMP Question # 278 Topic 28 Discussion

PMI Project Management Professional (2025 Version) PMP Question # 278 Topic 28 Discussion

PMP Exam Topic 28 Question 278 Discussion:
Question #: 278
Topic #: 28

A developer who has almost completed a required product feature for a prototype

leaves the company in the middle of an iteration. What should the project manager do?


A.

Review the backlog to reschedule the deliverable for a later iteration.


B.

Engage with stakeholders directly to review the iteration process.


C.

Determine whether other cross-functional team members are able to take over thework.


D.

Go to management and ask to hire a new external developer.