Question #: 277
Topic #: 28

A few key stakeholders are concerned about how the prefect team is planning to develop some features tor a new product. They know that the requirements associated with these features are unstable but are also highly strategic for adding value to the product and the customer.

What should the project manager do?


A.

Suggest an agile approach to refine these requirements and prioritize them according to the project objectives


B.

Validate the prioritization of all requirements with the sponsor and share the results with the stakeholders


C.

Review the project governance to validate the policies procedures and guidelines used to prioritize the project


D.

Ask the stakeholders to refine these requirements at a level of detail that becomes more stable and measurable